Three professors Dr. Gupta, Dr. Sharma, Dr. Singh are evaluating Answer script of a subject. Dr. Gupta is 40% more efficient than Dr. Sharma, who is 20% more efficient than Dr. Singh. Dr. Gupta takes 10 days less than Dr. Sharma to complete the evaluation work. Dr. Gupta starts the evaluation work and works for 10 days and then Dr, Sharma takes over. Dr. Sharma evaluates for next 15 days and then stops. In how many days, Dr. Singh can complete the remaining evaluation work?
7.2 days
9.5 days
11.5 days
None of these
The correct Answer is:A
To solve the problem step by step, we will first determine the efficiencies of the three professors and then calculate how much work they complete in the given time.
Step 1: Determine the efficiencies of Dr. Gupta, Dr. Sharma, and Dr. Singh.
Let the efficiency of Dr. Singh be S.
- Dr. Sharma is 20% more efficient than Dr. Singh:
Efficiency of Dr. Sharma=S+0.2S=1.2S
- Dr. Gupta is 40% more efficient than Dr. Sharma:
Efficiency of Dr. Gupta=1.2S+0.4(1.2S)=1.2S+0.48S=1.68S
Step 2: Determine the time taken by each professor to complete the evaluation work.
Let the total work be W.
- Time taken by Dr. Singh to complete the work:
TS=WS
- Time taken by Dr. Sharma to complete the work:
TSh=W1.2S
- Time taken by Dr. Gupta to complete the work:
TG=W1.68S
According to the problem, Dr. Gupta takes 10 days less than Dr. Sharma:
TSh−TG=10
Substituting the expressions for TSh and TG:
W1.2S−W1.68S=10
Step 3: Solve for W in terms of S.
To solve the equation, find a common denominator:
W⋅1.68−W⋅1.21.2⋅1.68S=10
W(1.68−1.2)2.016S=10
W(0.48)2.016S=10
W=10⋅2.016S0.48
W=42S
Step 4: Calculate the time taken by each professor.
Now we can find the time taken by each professor:
- Dr. Singh:
TS=WS=42SS=42 days
- Dr. Sharma:
TSh=W1.2S=42S1.2S=35 days
- Dr. Gupta:
TG=W1.68S=42S1.68S=25 days
Step 5: Calculate the work done by Dr. Gupta and Dr. Sharma.
- Work done by Dr. Gupta in 10 days:
WorkG=10⋅1.68S=16.8S
- Remaining work after Dr. Gupta:
Remaining Work=W−WorkG=42S−16.8S=25.2S
- Work done by Dr. Sharma in 15 days:
WorkSh=15⋅1.2S=18S
- Remaining work after Dr. Sharma:
Remaining Work=25.2S−18S=7.2S
Step 6: Calculate the time taken by Dr. Singh to complete the remaining work.
- Time taken by Dr. Singh to complete the remaining work:
TSingh=7.2SS=7.2 days
Final Answer:
Dr. Singh can complete the remaining evaluation work in 7.2 days.
---
Efficiency of Dr. Sharma=S+0.2S=1.2S
Efficiency of Dr. Gupta=1.2S+0.4(1.2S)=1.2S+0.48S=1.68S
TS=WS
TSh=W1.2S
TG=W1.68S
TSh−TG=10
W1.2S−W1.68S=10
W⋅1.68−W⋅1.21.2⋅1.68S=10
W(1.68−1.2)2.016S=10
W(0.48)2.016S=10
W=10⋅2.016S0.48
W=42S
- Dr. Singh:
TS=WS=42SS=42 days
- Dr. Sharma:
TSh=W1.2S=42S1.2S=35 days
- Dr. Gupta:
TG=W1.68S=42S1.68S=25 days
WorkG=10⋅1.68S=16.8S
Remaining Work=W−WorkG=42S−16.8S=25.2S
WorkSh=15⋅1.2S=18S
Remaining Work=25.2S−18S=7.2S
TSingh=7.2SS=7.2 days
Dr. Singh can complete the remaining evaluation work in 7.2 days.
Similar Questions
Knowledge Check
Who was Dr. Salim Ali
ASericulturistBGeologistsCSpace scientistDOrnithologistDr Andrew was working as an to Dr, Edward page-
Aassistant,Bclerk,Cchemist,Dcompounder.What made Dr.M.S. Swaminathan famous?
AHe Is a horiculturistBGeneticistCPlant breederDAll of these