A can finished one-third of a work in 5 days, B can finish 25th of the same workin 10days and C can finish 75% of the same work in 15 days. They work together for 6 days. The remaining workk will be finished by B along in :

A

3 days

B

2 days

C

5 days

D

112 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, let's break it down step by step.

Step 1: Determine the total work done by A, B, and C.

1. A's Work: A can finish 13 of the work in 5 days.
- Therefore, in 15 days (which is 3 times 5 days), A can finish the entire work.
- A's efficiency = 115 of the work per day.

2. B's Work: B can finish 25 of the work in 10 days.
- Therefore, in 25 days (which is 2.5 times 10 days), B can finish the entire work.
- B's efficiency = 125 of the work per day.

3. C's Work: C can finish 75% of the work in 15 days.
- 75% is equivalent to 34, so in 20 days (which is 150.75), C can finish the entire work.
- C's efficiency = 120 of the work per day.

Step 2: Calculate the combined efficiency of A, B, and C.

- A's efficiency = 115
- B's efficiency = 125
- C's efficiency = 120

To find the combined efficiency, we need to find a common denominator:
- The LCM of 15, 25, and 20 is 300.

Now, convert each efficiency to have a denominator of 300:
- A's efficiency = 20300
- B's efficiency = 12300
- C's efficiency = 15300

Combined efficiency = 20+12+15300=47300 of the work per day.

Step 3: Calculate the work done in 6 days.

- Work done in 6 days = 6×47300=282300 of the work.

Step 4: Calculate the remaining work.

- Total work = 1 (whole work)
- Work done in 6 days = 282300
- Remaining work = 1282300=300282300=18300=350 of the work.

Step 5: Calculate how long B will take to finish the remaining work.

- B's efficiency = 125 of the work per day.
- Time taken by B to finish the remaining work = Remaining work / B's efficiency
- Time = 350125=350×25=3×2550=7550=32 days or 112 days.

Final Answer:
The remaining work will be finished by B alone in 112 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?

    A24 days
    B18 days
    C20 days
    D16 days
  • A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

    A9 days
    B11 days
    C15 days
    D20 days
  • A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?

    A5
    B18
    C25
    D20