A can finished one-third of a work in 5 days, B can finish 25th of the same workin 10days and C can finish 75% of the same work in 15 days. They work together for 6 days. The remaining workk will be finished by B along in :
3 days
2 days
5 days
112 days
The correct Answer is:D
To solve the problem, let's break it down step by step.
Step 1: Determine the total work done by A, B, and C.
1. A's Work: A can finish 13 of the work in 5 days.
- Therefore, in 15 days (which is 3 times 5 days), A can finish the entire work.
- A's efficiency = 115 of the work per day.
2. B's Work: B can finish 25 of the work in 10 days.
- Therefore, in 25 days (which is 2.5 times 10 days), B can finish the entire work.
- B's efficiency = 125 of the work per day.
3. C's Work: C can finish 75% of the work in 15 days.
- 75% is equivalent to 34, so in 20 days (which is 150.75), C can finish the entire work.
- C's efficiency = 120 of the work per day.
Step 2: Calculate the combined efficiency of A, B, and C.
- A's efficiency = 115
- B's efficiency = 125
- C's efficiency = 120
To find the combined efficiency, we need to find a common denominator:
- The LCM of 15, 25, and 20 is 300.
Now, convert each efficiency to have a denominator of 300:
- A's efficiency = 20300
- B's efficiency = 12300
- C's efficiency = 15300
Combined efficiency = 20+12+15300=47300 of the work per day.
Step 3: Calculate the work done in 6 days.
- Work done in 6 days = 6×47300=282300 of the work.
Step 4: Calculate the remaining work.
- Total work = 1 (whole work)
- Work done in 6 days = 282300
- Remaining work = 1−282300=300−282300=18300=350 of the work.
Step 5: Calculate how long B will take to finish the remaining work.
- B's efficiency = 125 of the work per day.
- Time taken by B to finish the remaining work = Remaining work / B's efficiency
- Time = 350125=350×25=3×2550=7550=32 days or 112 days.
Final Answer:
The remaining work will be finished by B alone in 112 days.
---
- Therefore, in 15 days (which is 3 times 5 days), A can finish the entire work.
- A's efficiency = 115 of the work per day.
- Therefore, in 25 days (which is 2.5 times 10 days), B can finish the entire work.
- B's efficiency = 125 of the work per day.
- 75% is equivalent to 34, so in 20 days (which is 150.75), C can finish the entire work.
- C's efficiency = 120 of the work per day.
- B's efficiency = 125
- C's efficiency = 120
- The LCM of 15, 25, and 20 is 300.
- A's efficiency = 20300
- B's efficiency = 12300
- C's efficiency = 15300
- Work done in 6 days = 282300
- Remaining work = 1−282300=300−282300=18300=350 of the work.
- Time taken by B to finish the remaining work = Remaining work / B's efficiency
- Time = 350125=350×25=3×2550=7550=32 days or 112 days.
The remaining work will be finished by B alone in 112 days.
Similar Questions
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
View SolutionA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View Solution
Knowledge Check
A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 daysA can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
A9 daysB11 daysC15 daysD20 daysA can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
A5B18C25D20
A can do 15th of a work in 4 days and B can do 16th of the same work in 5 days. In how many days they can finish the work, if they work together?
View SolutionA can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?
View SolutionRam can do a piece of work in 6 days and Shyam can finish the same work in 12 days. How much work will be finished if both work together for 2 days ?
View SolutionA can do 1/5 th of a work in 4 days and B can do 1/6th of the same work in 5 days. In how many days they can finish the work, if they work together?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6
View Solution