Joe complete 14 th of a task in 10 days , and Jack can complete 25 th of the same task in 9 days. How long will Joe and Jack take to complete the task working together ?

A

938 days

B

6110 days

C

1425 days

D

17 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem of how long Joe and Jack will take to complete the task working together, we can follow these steps:

Step 1: Determine Joe's total time to complete the task
Joe completes 14 of the task in 10 days. To find out how long it takes him to complete the entire task, we can set up the equation:

Total time for Joe=10 days×4=40 days

Step 2: Determine Jack's total time to complete the task
Jack completes 25 of the task in 9 days. To find out how long it takes him to complete the entire task, we can set up the equation:

Total time for Jack=9 days×52=452 days=22.5 days

Step 3: Calculate the work rates (efficiencies) of Joe and Jack
The work rate (efficiency) is calculated as the total work divided by the total time taken. Since the total work can be considered as 1 unit of work:

- Joe's efficiency:
Efficiency of Joe=1 work40 days=140 work/day

- Jack's efficiency:
Efficiency of Jack=1 work22.5 days=122.5 work/day

Step 4: Find a common denominator to add efficiencies
To add the efficiencies, we need a common denominator. The least common multiple (LCM) of 40 and 22.5 can be calculated. However, we can also convert Jack's efficiency to a fraction with a denominator of 90 for easier addition:

Efficiency of Jack=122.5=490
Efficiency of Joe=140=2.2590=9360

Step 5: Combine the efficiencies
Now we can add the efficiencies:

Combined efficiency=140+122.5=9360+16360=25360

Step 6: Calculate the time taken to complete the task together
Now that we have the combined efficiency, we can find the total time taken to complete the task together:

Total time=1 workCombined efficiency=125360=36025=14.4 days

Step 7: Convert to mixed number
To express 14.4 days as a mixed number:

14.4 days=14 days+0.4 days=14 days+25 days

Thus, the final answer is:

Joe and Jack will take 14 days and 25 days to complete the task together.

Final Answer:
14 days and 2/5 days (Option C)

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Virat can complete a task a 20 days, whereas Anu can complete the same task in 15 days. How long will it take for Virat and Anu to complete the task if they worked together

    A12 12 days
    B5 days
    C847 days
    D1712days
  • Question 2 - Select One

    A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?

    A12 days
    B8 days
    C14 days
    D10 days
  • Question 3 - Select One

    X can complete 57 th part of a work in 10 days and Y can complete 34 th part of the same work in 9 days. In how many days will both complete 1321 st part of the total work ?

    A6
    B4
    C3
    D12