If ten men can do a job in ten days, what fraction of the job can be done by one man in one day?
120
110
12
1100
The correct Answer is:D
To solve the problem, we need to determine what fraction of the job can be completed by one man in one day, given that ten men can complete the job in ten days.
1. Understand the total work done by ten men in ten days:
- If 10 men can complete the job in 10 days, we can calculate the total work in terms of "man-days".
- Total work = Number of men × Number of days = 10 men × 10 days = 100 man-days.
2. Calculate the work done by one man in one day:
- Since the total work is 100 man-days, we need to find out how much work one man can do in one day.
- Work done by one man in one day = Total work / Number of men = 100 man-days / 10 men = 10 days.
3. Determine the fraction of the job done by one man in one day:
- The work done by one man in one day is 1/10th of the total work.
- Therefore, the fraction of the job that one man can complete in one day = 1/100.
4. Final Answer:
- Thus, the fraction of the job that can be done by one man in one day is 1/100.
- If 10 men can complete the job in 10 days, we can calculate the total work in terms of "man-days".
- Total work = Number of men × Number of days = 10 men × 10 days = 100 man-days.
- Since the total work is 100 man-days, we need to find out how much work one man can do in one day.
- Work done by one man in one day = Total work / Number of men = 100 man-days / 10 men = 10 days.
- The work done by one man in one day is 1/10th of the total work.
- Therefore, the fraction of the job that one man can complete in one day = 1/100.
- Thus, the fraction of the job that can be done by one man in one day is 1/100.
Similar Questions
Knowledge Check
If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
A114B712C184D172If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.
A130B1900C190D160One man and six women working together can do a job in 10 days. The same job is done by two men in 'p' days and by eight women in p+5 days. By what percentage is the efficiency of a man greater than that of a woman?
A300%B500%C600%D700%
A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
View SolutionWorking together, P and Q can do a job in 6 days, Q and R can do the same job in 10 days while P and R can do it in 5 days How long will it take, if all of them work together to complete the job?
View SolutionIf 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View Solution