G is twice as fast as S in doing work .If G can do a work in 30 days less than S ,how many days will they take to complete the work together ?
A.25
B. 20
C. 22
D. 15
D
B
A
C
The correct Answer is:B
To solve the problem, we need to determine how many days G and S will take to complete the work together, given that G is twice as fast as S and that G can complete the work in 30 days less than S.
1. Define Variables:
- Let the number of days S takes to complete the work be x.
- Since G is twice as fast as S, G will take x2 days to complete the same work.
2. Set Up the Equation:
- According to the problem, G takes 30 days less than S:
x2=x−30
3. Solve the Equation:
- Multiply both sides by 2 to eliminate the fraction:
x=2x−60
- Rearranging gives:
60=2x−x
x=60
4. Determine G's Days:
- Since S takes 60 days, G takes:
602=30 days
5. Calculate Work Done Per Day:
- Work done by S in one day:
Work by S=160 (units of work per day)
- Work done by G in one day:
Work by G=130 (units of work per day)
6. Combine Their Work:
- Together, the work done in one day by both G and S:
Total work per day=160+130
- To add these fractions, find a common denominator (which is 60):
160+260=360=120
7. Calculate Total Days to Complete Work Together:
- If they can do 120 of the work in one day, then the total number of days to complete the work together is:
Total days=1(120)=20 days
Final Answer:
Thus, G and S will take 20 days to complete the work together.
- Let the number of days S takes to complete the work be x.
- Since G is twice as fast as S, G will take x2 days to complete the same work.
- According to the problem, G takes 30 days less than S:
x2=x−30
- Multiply both sides by 2 to eliminate the fraction:
x=2x−60
- Rearranging gives:
60=2x−x
x=60
- Since S takes 60 days, G takes:
602=30 days
- Work done by S in one day:
Work by S=160 (units of work per day)
- Work done by G in one day:
Work by G=130 (units of work per day)
- Together, the work done in one day by both G and S:
Total work per day=160+130
- To add these fractions, find a common denominator (which is 60):
160+260=360=120
- If they can do 120 of the work in one day, then the total number of days to complete the work together is:
Total days=1(120)=20 days
Thus, G and S will take 20 days to complete the work together.
Similar Questions
Knowledge Check
10 pepole can do a work in 30 days .In how many days ,can 15 people complete double the work ?
A. 20
B. 25
C. 40
D. 45ACBDCBDA
A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionP can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
View Solution