40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find the ratio of number of new men to number of old men.
2:9
2:7
1:3
None of these
The correct Answer is:C
To solve the problem step by step, we will follow these calculations:
Step 1: Understand the given information
- 40 men can complete a project in 28 days.
- Due to the inclusion of more men, the project was completed in 34 of the time.
Step 2: Calculate the new time taken
The new time taken to complete the project is:
d2=34×28=21 days
Step 3: Set up the equation using the formula
We will use the formula for work, which states:
m1⋅d1w1=m2⋅d2w2
Where:
- m1=40 (initial number of men)
- d1=28 (initial days)
- m2=40+x (new number of men, where x is the number of new men)
- d2=21 (new days)
Since the work w is the same in both cases, we can cancel it out:
40⋅28=(40+x)⋅21
Step 4: Simplify the equation
Now we simplify:
1120=(40+x)⋅21
Expanding the right side:
1120=840+21x
Step 5: Solve for x
Rearranging the equation to isolate x:
1120−840=21x
280=21x
x=28021=403
Step 6: Find the ratio of new men to old men
Now we know the number of new men x=403 and the number of old men is 40. The ratio of new men to old men is:
Ratio=x40=40340=13
This can also be expressed as 1:3.
Final Answer
The ratio of the number of new men to the number of old men is 1:3.
---
- 40 men can complete a project in 28 days.
- Due to the inclusion of more men, the project was completed in 34 of the time.
The new time taken to complete the project is:
d2=34×28=21 days
We will use the formula for work, which states:
m1⋅d1w1=m2⋅d2w2
Where:
- m1=40 (initial number of men)
- d1=28 (initial days)
- m2=40+x (new number of men, where x is the number of new men)
- d2=21 (new days)
40⋅28=(40+x)⋅21
Now we simplify:
1120=(40+x)⋅21
Expanding the right side:
1120=840+21x
Rearranging the equation to isolate x:
1120−840=21x
280=21x
x=28021=403
Now we know the number of new men x=403 and the number of old men is 40. The ratio of new men to old men is:
Ratio=x40=40340=13
This can also be expressed as 1:3.
The ratio of the number of new men to the number of old men is 1:3.
Topper's Solved these Questions
- RATIO,PROPORTION AND VARIATIONBOOK - DISHA PUBLICATIONCHAPTER - RATIO,PROPORTION AND VARIATIONEXERCISE - Practice Exercises (Expert Level)
12 Videos
- QUADRATIC AND CUBIC EQUATIONSBOOK - DISHA PUBLICATIONCHAPTER - QUADRATIC AND CUBIC EQUATIONSEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
Similar Questions
Out of the 144 persons working in an office, 56 are men and the remaining are women. Find the ratio of number of women to number of men.
View SolutionOf the 288 persons working in a company, 112 are men and the remaining are women. Find the ratio of the number of
men to the total number of persons.
View Solution
Knowledge Check
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
A38B28C19D17Three men and 5 women together can finish a job in 3 days. Working on the same job 3 women take 5 days more than the time required by 2 men. What is the ratio of efficiency of a man to a woman?
A2:1B3:2C5:2D4:1Certain men can do a piece of work in 22 days. If the number of men decreses by 55, then they will take 11 days more to comlete the same work. Find the number of men present intially.
A165B155C185D175
Of the 288 persons working in a company, 112 are men and the remaining are women. Find the ratio of the number of
men to that of women
View SolutionIf 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .
View SolutionWork done is directly proportional to the number of men working on it.
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View Solution