A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more
The correct Answer is:Rs 27,750
Step by step video, text & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Updated on:21/07/2023Topper's Solved these Questions
- ARITHMETIC PROGRESSIONS BOOK - MTG IIT JEE FOUNDATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - NCERT SECTION EXERCISE 5.4
5 Videos
- ARITHMETIC PROGRESSIONS BOOK - MTG IIT JEE FOUNDATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - EXERCISE (MULTIPLE CHOICE QUESTION )(LEVEL 1 )
35 Videos
- ARITHMETIC PROGRESSIONS BOOK - MTG IIT JEE FOUNDATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - NCERT SECTION EXERCISE 5.2
26 Videos
- AREAS RELATED TO CIRCLESBOOK - MTG IIT JEE FOUNDATIONCHAPTER - AREAS RELATED TO CIRCLESEXERCISE - OLYMPIAD/HOTS CORNER
30 Videos
- CIRCLESBOOK - MTG IIT JEE FOUNDATIONCHAPTER - CIRCLESEXERCISE - Olympiad/HOTS Corner
30 Videos
Similar Questions
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
View Solution
Knowledge Check
If you save Rs. 1 today, Rs. 2 the next day, Rs. 3 the succeeding day and so on, what will be your total savings in 365 days?
A66579B66795C56795Dnone of theseThe hostel canteen charges Rs 25 for lunch and Rs 8 for milk for each day. Then, how much money do you spend in 5 days on these things?
ARs 120BRs 135CRs 165DRs 185
A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
View SolutionA woker is paid Rs 200 for 8 days work. If he works for 20 days, how much will he get?
View SolutionAverage expenditure of four days of a boy is Rs.63. If first day he spent Rs.110, second day he spent Rs.95, third day, he spent Rs. 25, how much did he spend on fourth day?
View SolutionA can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240.If the wages are divided in proportion to the work done by them, find what each will get. a. A Rs. 24, B Rs. 54 and C Rs. 162 b. A Rs. 22, B Rs. 50 and C Rs. 132 c. A Rs. 26, B Rs. 52 and C Rs. 142 d. A Rs. 20, B Rs. 44 and C Rs. 182
View SolutionA labourer is engaged for 20 days on the condition that he will receive Rs 60 for each day, he works and he will be fined Rs 5 for each day, he is absent. If he receives Rs 745 in all, for how many days he remained absent?
View SolutionA worker is paid Rs. 162.50 for 5 days. What should be paid to him for 28 days?
View Solution