A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?Solution in Punjabi
Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
In which of the following situations, does the list of numbers involved make an arithmetic progression, and why ? :- The taxi fare after each km when the fare is $ 15 for the first km and $ 8 for each additional km.
View SolutionThe cost of fencing a circular field at the rate of ₹ 24 per metre is ₹ 5280. The field is to be ploughed al the rate of ₹ 0.50 per m2. Find the cost of ploughing the field (Take π=227).
View SolutionProve that in two concentric circles, the chord of the larger circle, which touches the smaller circle, is bisected at the point of contact.
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day,Rs.250 for second day,Rs.300 for thirdday and so on.If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
View Solutionनिर्माण कार्य से संबंधित किसी ठेके में, एक निश्चित तिथि के बाद कार्य को विलम्ब से पूरा करने के लिए, जुर्माना लगाने का प्रावधान इस प्रकार हैं : पहले दिन के लिए ₹ 200, दूसरे दिन के लिए ₹ 250, तीसरे दिन के लिए ₹ 300 इत्यादि, अर्थात प्रत्येक उत्तरोत्तर दिन का जुर्माना अपने से ठीक पहले दिन के जुर्माने से ₹50 अधिक हैं । एक ठेकेदार को जुर्माने के रूप में कितनी राशि अदा करनी पड़ेगी, यदि वह इस कार्य में 30 दिन का विलम्ब कर देता हैं?
View Solutionनिर्माण कार्य से संबंधित किसी ठेके में, एक निश्चित तिथि के बाद कार्य को विलम्ब सेपूरा करने के लिए, जुर्माना लगाने का प्रावधान इस प्रकार है: पहले दिन के लिए रू0 200, दूसरे दिन के लिए रू0 250, तीसरे दिन के लिए रू0 300 इत्यादि। अर्थात प्रत्येक उत्तरोत्तर दिन का जुर्माना अपने से ठीक पहले दिन के जुर्माने से रू0 50 अधिक है। एक ठेकेदार को जुर्माने के रूप में कितनी राशि अदा करनी पड़ेगी, यदि वह इस कार्य को 30 दिन में विलम्ब से पूरा करता है?
View SolutionA contract on construction job specific a penalty for delay of completion beyond a certain date as follows : Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?
View SolutionA contract on construction job specifies a penalty for delay of completionbeyond a certain data as follows: Rs200 for the first day , Rs250 for the second day, Rs300 for the third day , etc., the penalty for each succeeding day being Rs50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 30 days ?
View SolutionA construction company will be penalised each day for delay in construction of a bridge. The penalty will be Rs 4000 for the first day and will increase by Rs 1000 for each following day. Based on its budget, the company can afford to pay a maximum of Rs 1,65,000 towards penalty. Find the maximum number of days by which the construction of work can be delayed.
View SolutionIf the work of a building is completed late after a certain amount of time, that is. The form was fined. It is as follows: Rs.200 for first day, Rs.250 for second day, Rs.300 for 3rd day. Every day. The penalty is' Rs.50 a pound higher than the previous day's fine. If a contractor takes more than 30 days to complete a job, calculate the penalty he must pay?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : Rs 200 for the first day . Rs 250 for the second day , Rs 300 for the third day , etc. the penalty for each succeeding day being Rs50 more than for the preceding day. How much money the contractor has to pay as penalty , if the has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?
View Solution