The construction of our main road began in summer on 6/6/2010. It took 1 yr 3 month 18 days to finish the work. Let's calculate to find on which date the road construction work was completed. Solution in Bengali
Step by step video & image solution for The construction of our main road began in summer on 6/6/2010. It took 1 yr 3 month 18 days to finish the work. Let's calculate to find on which date the road construction work was completed. by Maths experts to help you in doubts & scoring excellent marks in Class 6 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
Measuring with , a scale, the length of my pen is found to be 14.7 cm and the length of my sisters pen in 15.2 cm Let us find the lengths of pens in millimetre.
View SolutionLet's do mentally - (a) How much is 12 of Rs. 10?
View SolutionA contractor calculated that he could finish the construction of a road in 40 working days. He knew appointed 32 people and made them work for 6 hours a day for 5 days in a week, the work would finish But he could arrange for only 20 workers. He decided to make them work for 8 hours a day for 6 days a week Will they complete the work in time? If not, how many more days will they take?
View Solutionएक ठेकेदार ने 40 दिन में सड़क बनाने का टेका लिया और इस कार्य में लिए उसने 25 पुरुषो को काम पर लगाया । 24 दिन के पश्ताप उसने पाया कि केवल 13 भाग सड़क बन पाया है तो 4 दिन पहले काम ख़त्म करने के लिए कितने अतिरिक्त पुरुष काम पर लगाने होंगे ?
View Solution639 व्यक्ति 5 घंटे प्रतिदिन काम करके 12 दिनों में एक सड़क की मरम्मत करते है 30 व्यक्ति 6 घण्टे प्रतिदिन काम करके कितने दिनों में काम ख़त्म करेंगे ?
View Solution3 पुरुष किसी काम को 6 दिनों में समाप्त कर सकते है उनके काम शुरू करने के 2 दिनों के वे कितने दिनों में समाप्त करेंगे ?
View SolutionThe project of the road construction (work) has crossed its first deadline as far as per-monsoon road works are concrened. In the major city the road works are given great emphasis and these are the places where road work has been completed. Which of the following can be concluded from the statements given above ?
View SolutionWhich type of road is constructed under the road?
View SolutionWhich type of road is constructed under the road?
View Solutionআমাদের পাড়ার প্রধান রাস্তা তৈরির কাজ গ্রীস্মকালের 6/6/2010 তারিখ শুরু হয়েছিল। রাস্তা তৈরির কাজ সম্পূর্ণ করতে 1 বছর 3 মাস 18 দিন সময় লেগেছিল। হিসাব করে দেখো কত তারিখে রাস্তা তৈরির কাজ শেষ হয়েছে?
View Solutionআমাদের পাড়ার প্রধান রাস্তা তৈরির কাজ গ্রীস্মকালের 6/6/2010 তারিখ শুরু হয়েছিল। রাস্তা তৈরির কাজ সম্পূর্ণ করতে 1 বছর 3 মাস 18 দিন সময় লেগেছিল। হিসাব করে দেখো কত তারিখে রাস্তা তৈরির কাজ শেষ হয়েছে?
View SolutionIn 6 days, 5 masons finished only half of the work. But 3 masons took more days to finish the remaining the work. Why so?
View Solutionएक ठेकेदार ने 40 दिन में एक सडक बनाने का निर्णय लिया और 25 व्यक्ति काम पर लगाये। 24 दिन बाद काम का एक तिहाई हिस्सा पूरा हो पाया। कितने अतिरिक्त व्यक्तियों को काम पर लगाया जाये ताकि काम ठीक समय से 4 दिन पहले समाप्त हो सके।
View SolutionThirty men were engged to construct a road in 2 months. But 6 men did not come to work at all. How many days will it take to construct the road ?
(Assume that 2 months = 60 days.)
View Solution7 men working 8 hours a day can complete 2/3 of a work in 36 days. In how many days will the remaining 1/3 of the same work be finished, if 24 men work 6 hours a day?
View Solution