A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:₹ 27750


Total penalty = ₹ (200 + 250 + 300 +… up to 30 terms).
T30=(200+29×50)=1650
required sum={302(200+1650)}=27750

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If you save Rs. 1 today, Rs. 2 the next day, Rs. 3 the succeeding day and so on, what will be your total savings in 365 days?

    A66579
    B66795
    C56795
    Dnone of these
  • The hostel canteen charges Rs 25 for lunch and Rs 8 for milk for each day. Then, how much money do you spend in 5 days on these things?

    ARs 120
    BRs 135
    CRs 165
    DRs 185