The efficiencies of A, B, and C are in the ratio 2 : 5 : 3. Working together, they can complete a task in 12 days. In how many days can A alone complete 30% of that task ?
15
16
20
18
The correct Answer is:D
To solve the problem, we will follow these steps:
Step 1: Determine the total efficiency of A, B, and C
The efficiencies of A, B, and C are given in the ratio 2 : 5 : 3.
Let the efficiencies be:
- Efficiency of A = 2x
- Efficiency of B = 5x
- Efficiency of C = 3x
Step 2: Calculate the total efficiency
The total efficiency of A, B, and C combined is:
Total Efficiency=2x+5x+3x=10x
Step 3: Calculate the total work done
We know that working together, A, B, and C can complete the task in 12 days. Therefore, the total work (W) can be calculated as:
W=Total Efficiency×Time
W=10x×12=120x
Step 4: Calculate 30% of the total work
To find out how much work A needs to complete, we calculate 30% of the total work:
30% of W=0.3×120x=36x
Step 5: Calculate the time taken by A to complete 36x work
A's efficiency is 2x. The time (T) taken by A to complete 36x work can be calculated using the formula:
T=WorkEfficiency
T=36x2x=18 days
Conclusion
Thus, A alone can complete 30% of the task in 18 days.
---
The efficiencies of A, B, and C are given in the ratio 2 : 5 : 3.
- Efficiency of A = 2x
- Efficiency of B = 5x
- Efficiency of C = 3x
The total efficiency of A, B, and C combined is:
Total Efficiency=2x+5x+3x=10x
We know that working together, A, B, and C can complete the task in 12 days. Therefore, the total work (W) can be calculated as:
W=Total Efficiency×Time
W=10x×12=120x
To find out how much work A needs to complete, we calculate 30% of the total work:
30% of W=0.3×120x=36x
A's efficiency is 2x. The time (T) taken by A to complete 36x work can be calculated using the formula:
T=WorkEfficiency
T=36x2x=18 days
Thus, A alone can complete 30% of the task in 18 days.
Similar Questions
The efficiency of A, B and C are in the ratio 5:6:9. Working together, they can complete a work in 18 day. In how many days can B alone complete 25% of that work?
View SolutionThe efficiencies of A, B and C are in the ratio of 5:3:2. Working together, they can complete a task in 21 hours. In how many hours will B alone complete 40% of that task?
A, B और C की कार्य क्षमता का अनुपात 5 : 3 : 2 है | एक साथ कार्य करते हुए, वे किसी कार्य को 21 घंटों में कर सकते हैं | इस कार्य का 40% भाग पूरा करने में B को अकेले कितने घंटे लगेंगे ?View Solution
Knowledge Check
- Question 1 - Select One
The efficiencies of A, B and C are in the ratio 2:5:3. Working together, they can complete a task in 12 days. In how many days can A alone complete 30% of that task?
A, B और C की कार्य क्षमता का अनुपात 2 : 5 : 3 है | एक साथ कार्य करते हुए, वे किसी कार्य को 12 दिनों में पूरा कर सकते हैं | A अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?A15B16C20D18 - Question 2 - Select One
The efficiencies of A, B and C are in the ratio of 2: 3: 5. Working together, they can complete a task in 6 days. In how many days will A alone complete 20% of that task?
A8B5C6D4 - Question 3 - Select One
The efficiencies of A, B and C are in the ratio 2:5:3. Working together, they can compete a task in 9 days. In how many days will C alone complete 40% of that task ?
A14B16C15D12
The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working together, they can complete a work in 10 days. In how many days will, A alone be able to complete 30% of that work?
A, B और C की कार्य क्षमता 2 : 5: 7 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | इस कार्य का 30% भाग समाप्त करने में A को अकेले कितना समय (दिन ) लगेगा ?View SolutionThe efficiencies of A,B and C are in the ratio 4 : 5 : 6. Working together, they can complete a work in 12 days. In how many days will A alone be able to complete that work?
A, B तथा C की कार्य क्षमता 4 : 5 : 6 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 12 दिन में पूरा कर सकते हैं | A अकेले इस कार्य को कितने दिन में कर पाएगा ?View SolutionThe efficiencies of A,B and C are in the ratio 4 : 5 : 6. Working together, they can complete a work in 12 days. In how many days will A alone be able to complete that work?
A, B तथा C की कार्य क्षमता 4 : 5 : 6 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 12 दिन में पूरा कर सकते हैं | A अकेले इस कार्य को कितने दिन में कर पाएगा ?View SolutionThe efficiencies of A, B and C are in the ratio 2 : 5 : 7 working together, they can complete a work in 10 days. In how many days will, A alone be able to complete 30% of that work?
A, B और C की कार्य क्षमता 2 : 5: 7 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | इस कार्य का 30% भाग समाप्त करने में A को अकेले कितना समय (दिन ) लगेगा ?View SolutionA is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 20 days. In how many days will C alone complete 30% of that task?
A, B से 50% अधिक कार्य कुशल है तथा C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 20 दिनों में पूरा कर सकते हैं | C अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?View Solution