A and B can complete a piece of work in 10 and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of ₹60, what are their individual shares ?
₹20,₹40
₹24,₹36
₹25,₹35
₹30,₹30
The correct Answer is:B
To solve the problem step by step, we will determine how much work A and B do individually and then calculate their shares based on the total earnings of ₹60.
Step 1: Determine the work rates of A and B
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=110 (work per day)
- B can complete the work in 15 days, so B's work rate is:
Work rate of B=115 (work per day)
Step 2: Calculate the work done by B in the first 5 days
- In 5 days, B will complete:
Work done by B in 5 days=5×115=515=13
Step 3: Calculate the remaining work
- The total work is considered as 1 (whole work). After B works for 5 days, the remaining work is:
Remaining work=1−13=23
Step 4: Calculate the combined work rate of A and B
- When A joins B, their combined work rate is:
Combined work rate=110+115
- To add these fractions, find a common denominator (which is 30):
110=330,115=230
Combined work rate=330+230=530=16
Step 5: Calculate the time taken to complete the remaining work
- The remaining work of 23 will take:
Time=Remaining workCombined work rate=2316=23×6=4 days
Step 6: Calculate the total work done by A and B
- Total work done by B:
- B worked for 5 days initially and then worked for 4 days with A:
Total work by B=5+4=9 days
- Total work done by A:
- A joined after 5 days and worked for 4 days:
Total work by A=4 days
Step 7: Calculate the shares based on work done
- Total parts of work done:
- Work done by A:
Work by A=4×110=410=25
- Work done by B:
Work by B=9×115=915=35
Step 8: Calculate the earnings based on work done
- Total earnings = ₹60
- A's share:
A's share=Total earnings×Work by ATotal work=60×2/51=60×0.4=₹24
- B's share:
B's share=Total earnings×Work by BTotal work=60×3/51=60×0.6=₹36
Final Shares:
- A's share = ₹24
- B's share = ₹36
---
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=110 (work per day)
- B can complete the work in 15 days, so B's work rate is:
Work rate of B=115 (work per day)
- In 5 days, B will complete:
Work done by B in 5 days=5×115=515=13
- The total work is considered as 1 (whole work). After B works for 5 days, the remaining work is:
Remaining work=1−13=23
- When A joins B, their combined work rate is:
Combined work rate=110+115
- To add these fractions, find a common denominator (which is 30):
110=330,115=230
Combined work rate=330+230=530=16
- The remaining work of 23 will take:
Time=Remaining workCombined work rate=2316=23×6=4 days
- Total work done by B:
- B worked for 5 days initially and then worked for 4 days with A:
Total work by B=5+4=9 days
- Total work done by A:
- A joined after 5 days and worked for 4 days:
Total work by A=4 days
- Total parts of work done:
- Work done by A:
Work by A=4×110=410=25
- Work done by B:
Work by B=9×115=915=35
- Total earnings = ₹60
- A's share:
A's share=Total earnings×Work by ATotal work=60×2/51=60×0.4=₹24
- B's share:
B's share=Total earnings×Work by BTotal work=60×3/51=60×0.6=₹36
- A's share = ₹24
- B's share = ₹36
Topper's Solved these Questions
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND DISTANCE BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )
3 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A can complete a work in 10 days and B can in 15 days. B starts the work and is joined by A after 5 days. If they earn a total of Y 65, what are their individual shares?
View SolutionA and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work
View Solution
Knowledge Check
A and B can complete a piece of work in 10 and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of ₹60, what are their individual shares ?
A₹ 20, ₹ 40B₹ 24, ₹ 36C₹ 25, ₹ 35D₹ 30, ₹ 30A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2
A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
View SolutionWorking individually, A and B can complete a piece of work in 30 days and 45 days respectively. If B joins A after some days and the whole work is completed in 20 days from the beginning, after how many days does B join A ?
View Solution