Two machines are capable of doing the same work. Should they have the same power?
To determine whether two machines capable of doing the same work should have the same power, we can analyze the definitions and relationships between work, power, and time.
1. Understanding Work and Power:
- Work (W) is defined as the energy transferred when a force is applied over a distance.
- Power (P) is defined as the rate at which work is done. Mathematically, it is expressed as:
P=WT
where W is the work done and T is the time taken to do that work.
2. Assuming Two Machines:
- Let’s denote the work done by both machines as W. Thus, both machines perform the same amount of work.
3. Different Times for Each Machine:
- Let’s say Machine 1 takes time T1 to complete the work, and Machine 2 takes time T2.
- The power for Machine 1 can be expressed as:
P1=WT1
- Similarly, the power for Machine 2 can be expressed as:
P2=WT2
4. Comparing Powers:
- Since both machines do the same work, the only factor that can affect their power is the time taken to complete that work.
- If T1 is different from T2, then P1 will not necessarily equal P2. Specifically:
P1≠P2ifT1≠T2
5. Conclusion:
- Therefore, it is not necessary for the two machines to have the same power, even though they perform the same work. Their power can vary depending on the time taken to do that work.
Final Answer:
No, the two machines do not necessarily have to have the same power, as power depends on the time taken to do the same amount of work.
- Work (W) is defined as the energy transferred when a force is applied over a distance.
- Power (P) is defined as the rate at which work is done. Mathematically, it is expressed as:
P=WT
where W is the work done and T is the time taken to do that work.
- Let’s denote the work done by both machines as W. Thus, both machines perform the same amount of work.
- Let’s say Machine 1 takes time T1 to complete the work, and Machine 2 takes time T2.
- The power for Machine 1 can be expressed as:
P1=WT1
- Similarly, the power for Machine 2 can be expressed as:
P2=WT2
- Since both machines do the same work, the only factor that can affect their power is the time taken to complete that work.
- If T1 is different from T2, then P1 will not necessarily equal P2. Specifically:
P1≠P2ifT1≠T2
- Therefore, it is not necessary for the two machines to have the same power, even though they perform the same work. Their power can vary depending on the time taken to do that work.
No, the two machines do not necessarily have to have the same power, as power depends on the time taken to do the same amount of work.
Similar Questions
Knowledge Check
Raman can do a work in 5 days jatin can do the same work in 7 days and sachin can do the same work in 9 days if they do the same work together and they are paid ₹2860 then what is the share of raman
A1260B700C900D870Which of these animals are placed in the same family but do not have the same genus ?
Adog and catBtiger and dogCdog and lionDcat and leopardA can do a work in 8 days , B can do the same work in 10 days and C can do the same work in 12 days . If all three of them do the same work together and they are paid Rs. 7400, what is the share (in Rs.) of B ?
A2600B3000C2400D2000
Do water and ice have the same specific heats?
View SolutionDo water and ice have the same specific heats?
View SolutionX can do a piece of work in 6 days while Y can do the same work in 8 days. Find in how many days X and Y together can do the same work?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
One day's work of X is 1/6 one day's work of Y is 1/8
X can do a piece of work in 6 days and Y can do the same work in 8 days.
X and Y together can do the same work in 337 days.
One day's work of X and Y=724
View SolutionX can do a piece of work in 6 days while Y can do the same work in 8 days. Find in how many days X and Y together can do the same work?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
One day's work of X is 1/6 one day's work of Y is 1/8
X can do a piece of work in 6 days and Y can do the same work in 8 days.
X and Y together can do the same work in 337 days.
One day's work of X and Y=724
View SolutionA can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View Solution