The MGNREGA aims at enhancing livelihood security of the rural poor by providing at least __________ days of guaranteed wage empolyment in a financial year to every household whose adult members volunteer to do unskilled manual work .
100 days
110 days
150 days
50 days
The correct Answer is:a
The MGNREGA aims at enhancing livelihood security of the rural poor by providing at least 100 days of guaranted wage employment in a financial year to every household whose adult members volunteer to do unskilled manual work.
Topper's Solved these Questions
Similar Questions
The happiest situation would be to provide employment assurance of say 100 days in a year to all the households which are below poverty line. Assuming that all the persons would not offer themselves for casual manual work, let us say only 30 million persons would come for such works. As the average cost of generation of one man-day under the Jawahar Rozgar Yojana and also under the Employment Assurance Scheme is Rs 45/-, the total requirement would be about Rs. 13500 crore per year. This requirement will also build up gradually as it is dependent on monsoons, wage levels and cost of material, etc. The current allocations under various wage employment programmes are, however, far less than required for such an employment assurance scenario.
In the year 2000 AD the cost of generation of one man-day under the EAS would be more than Rs 45.View SolutionThe happiest situation would be to provide employment assurance of say 100 days in a year to all the households which are below poverty line. Assuming that all the persons would not offer themselves for casual manual work, let us say only 30 million persons would come for such works. As the average cost of generation of one man-day under the Jawahar Rozgar Yojana and also under the Employment Assurance Scheme is Rs 45/-, the total requirement would be about Rs. 13500 crore per year. This requirement will also build up gradually as it is dependent on monsoons, wage levels and cost of material, etc. The current allocations under various wage employment programmes are, however, far less than required for such an employment assurance scenario.
The Jawahar Rozgar Yojana and the EAS would provide employment to as many persons as needed.View Solution
Knowledge Check
- Question 1 - Select One
Which of the following can be associated with MGNREGA programme?
1. It provides wage employment to every household whose adult members volunteer to do unskilled manual work.
2. It focuses on strengthening of natural resource management.
3. It encourages sustainable development.
Select the correct answer using the codes given below:A1 onlyB1 and 2 onlyC1 and 3 onlyD1, 2 and 3 - Question 2 - Select One
Consider the following statements
A. Mahatma Gandhi NREGA was enacted by Government of India in 2005.
B. It provides 100 days guaranteed employment in every financial year to adults of rural household.
Among these which statement is correct?AOnly ABOnly BCBoth A and BDNone of these - Question 3 - Select One
Delays of several months in National Rural Employment Guarantee , Scheme (NREGS) wage payments and work sites where labourers have lost all hope of being paid at all have become the norm in many states. How are workers who exist on the margins of subsistence supposed to feed their families? Under the scheme, workers must be paid within 15 days, failing which they are entitled, to compensation under the Payment of Wages Act - upto 3000 per aggrieved worker. In reality, compensation is received in only a few isolated instances. It is often argued by officials that the main reason for the delay is the inability ofbanks and post offices to handle mass payments of NREGS wages. Though there is a grain of truth in this·, as a diagnosis it is misleading. The 'jam' in the banking system has been the result of the hasty switch to bank payments imposed by the Central Government against the recommendation of the Central Employment Guarantee Council which advocated a gradual transition starting with villages relatively close to the nearest bank. However, delays are not confined solely to the banking system. Operational hurdles include implementing agencies taking more than fifteen days to issue payment orders, viewing of work measurement as a cumbersome process resulting in procrastination by the engineering staff and non maintenance of muster rolls and job card etc. But behind these delays lies a deeper and deliberate 'backlash.' against the NREGS. With bank payments making it much harder to embezzle NREGS funds, the programme is seen as a headache by many government functionaries the workload has remained without the "inducements". Slowing down wage payments is a convenient way of sabotaging the scheme because workers will desert NREGS worksites.
The common sense solution advocated by the government is to adopt the business correspondent model. Where in bank agents will go to villages to make cash payments and duly record them on handheld, electronic devices. This solution is based on the wrong diagnosis that distancP. separating villages from banks is the main issue. In order to accelerate payments, clear timelines for every step of the payment process should be incorporated into the system as Programme Officers often have no data on delays and cannot exert due pressure to remedy the situation. Workers are both clueless and powerless with no provision for them to air their grievances and seek redress. In drought affected areas the system of piece rate work can be dispensed with where work measurement is not completed within a week and wages may be paid on the basis of attendance. Buffer funds can be provided to gram panchayats and post offices to avoid bottlenecks in the flow of funds. Partial advances could also be considered provided wage payments are meticulously tracked. But failure to recognise problems and unwillingness to remedy them will remain major threats to the NREGS.
Which of the following factors has not been responsible for untimely payment ofNREGS wages?ACommunication delays between agencies implementing the schemeBImproper record keepingCBehind schedule release of payments by banksDDrought conditions prevalent in the country
The happiest situation would be to provide employment assurance of say 100 days in a year to all the households which are below poverty line. Assuming that all the persons would not offer themselves for casual manual work, let us say only 30 million persons would come for such works. As the average cost of generation of one man-day under the Jawahar Rozgar Yojana and also under the Employment Assurance Scheme is Rs 45/-, the total requirement would be about Rs. 13500 crore per year. This requirement will also build up gradually as it is dependent on monsoons, wage levels and cost of material, etc. The current allocations under various wage employment programmes are, however, far less than required for such an employment assurance scenario.
Weather conditions have some role to play in the fund allocation of employment schemes.View SolutionThe happiest situation would be to provide employment assurance of say 100 days in a year to all the households which are below poverty line. Assuming that all the persons would not offer themselves for casual manual work, let us say only 30 million persons would come for such works. As the average cost of generation of one man-day under the Jawahar Rozgar Yojana and also under the Employment Assurance Scheme is Rs 45/-, the total requirement would be about Rs. 13500 crore per year. This requirement will also build up gradually as it is dependent on monsoons, wage levels and cost of material, etc. The current allocations under various wage employment programmes are, however, far less than required for such an employment assurance scenario.
The Jawahar Rozgar Yojana is backed with adequate funds and political will.View SolutionThe happiest situation would be to provide employment assurance of say 100 days in a year to all the households which are below poverty line. Assuming that all the persons would not offer themselves for casual manual work, let us say only 30 million persons would come for such works. As the average cost of generation of one man-day under the Jawahar Rozgar Yojana and also under the Employment Assurance Scheme is Rs 45/-, the total requirement would be about Rs. 13500 crore per year. This requirement will also build up gradually as it is dependent on monsoons, wage levels and cost of material, etc. The current allocations under various wage employment programmes are, however, far less than required for such an employment assurance scenario.
There are, actually, less than 30 million persons below the poverty line.View SolutionDelays of several months in National Rural Employment Guarantee , Scheme (NREGS) wage payments and work sites where labourers have lost all hope of being paid at all have become the norm in many states. How are workers who exist on the margins of subsistence supposed to feed their families? Under the scheme, workers must be paid within 15 days, failing which they are entitled, to compensation under the Payment of Wages Act - upto 3000 per aggrieved worker. In reality, compensation is received in only a few isolated instances. It is often argued by officials that the main reason for the delay is the inability ofbanks and post offices to handle mass payments of NREGS wages. Though there is a grain of truth in this·, as a diagnosis it is misleading. The 'jam' in the banking system has been the result of the hasty switch to bank payments imposed by the Central Government against the recommendation of the Central Employment Guarantee Council which advocated a gradual transition starting with villages relatively close to the nearest bank. However, delays are not confined solely to the banking system. Operational hurdles include implementing agencies taking more than fifteen days to issue payment orders, viewing of work measurement as a cumbersome process resulting in procrastination by the engineering staff and non maintenance of muster rolls and job card etc. But behind these delays lies a deeper and deliberate 'backlash.' against the NREGS. With bank payments making it much harder to embezzle NREGS funds, the programme is seen as a headache by many government functionaries the workload has remained without the "inducements". Slowing down wage payments is a convenient way of sabotaging the scheme because workers will desert NREGS worksites.
The common sense solution advocated by the government is to adopt the business correspondent model. Where in bank agents will go to villages to make cash payments and duly record them on handheld, electronic devices. This solution is based on the wrong diagnosis that distancP. separating villages from banks is the main issue. In order to accelerate payments, clear timelines for every step of the payment process should be incorporated into the system as Programme Officers often have no data on delays and cannot exert due pressure to remedy the situation. Workers are both clueless and powerless with no provision for them to air their grievances and seek redress. In drought affected areas the system of piece rate work can be dispensed with where work measurement is not completed within a week and wages may be paid on the basis of attendance. Buffer funds can be provided to gram panchayats and post offices to avoid bottlenecks in the flow of funds. Partial advances could also be considered provided wage payments are meticulously tracked. But failure to recognise problems and unwillingness to remedy them will remain major threats to the NREGS.
To which of the following has the author attributed the delay in wage payments?View SolutionDelays of several months in National Rural Employment Guarantee , Scheme (NREGS) wage payments and work sites where labourers have lost all hope of being paid at all have become the norm in many states. How are workers who exist on the margins of subsistence supposed to feed their families? Under the scheme, workers must be paid within 15 days, failing which they are entitled, to compensation under the Payment of Wages Act - upto 3000 per aggrieved worker. In reality, compensation is received in only a few isolated instances. It is often argued by officials that the main reason for the delay is the inability ofbanks and post offices to handle mass payments of NREGS wages. Though there is a grain of truth in this·, as a diagnosis it is misleading. The 'jam' in the banking system has been the result of the hasty switch to bank payments imposed by the Central Government against the recommendation of the Central Employment Guarantee Council which advocated a gradual transition starting with villages relatively close to the nearest bank. However, delays are not confined solely to the banking system. Operational hurdles include implementing agencies taking more than fifteen days to issue payment orders, viewing of work measurement as a cumbersome process resulting in procrastination by the engineering staff and non maintenance of muster rolls and job card etc. But behind these delays lies a deeper and deliberate 'backlash.' against the NREGS. With bank payments making it much harder to embezzle NREGS funds, the programme is seen as a headache by many government functionaries the workload has remained without the "inducements". Slowing down wage payments is a convenient way of sabotaging the scheme because workers will desert NREGS worksites.
The common sense solution advocated by the government is to adopt the business correspondent model. Where in bank agents will go to villages to make cash payments and duly record them on handheld, electronic devices. This solution is based on the wrong diagnosis that distancP. separating villages from banks is the main issue. In order to accelerate payments, clear timelines for every step of the payment process should be incorporated into the system as Programme Officers often have no data on delays and cannot exert due pressure to remedy the situation. Workers are both clueless and powerless with no provision for them to air their grievances and seek redress. In drought affected areas the system of piece rate work can be dispensed with where work measurement is not completed within a week and wages may be paid on the basis of attendance. Buffer funds can be provided to gram panchayats and post offices to avoid bottlenecks in the flow of funds. Partial advances could also be considered provided wage payments are meticulously tracked. But failure to recognise problems and unwillingness to remedy them will remain major threats to the NREGS.
What has the outcome of disbursing NREGS wages through banks been?View Solution