A person has undertaken a construction job. The probabilities are 0.65 that there will be strike. 0.80 that the construction job will be completed on time if there is no strike, and 0.32 that the construction job will be completed on time if ther
Probability of having strike
P(A)=0.05
Probability of not having strike
P(¯¯¯A)=1−0.65=0.35
E= work finished in time
probability of work comleted on time is
P(EA)=0.32
probability of completion of work if strike is not happening P(EA)=0.80
Probability job will be completed on time
P(E)=P(A).P(EA)+P(¯¯¯A)⋅P(E¯¯¯A)=0.65×0.32+0.35×0.80=0.208+ 0.280=0.488 Required probability =0.488
Topper's Solved these Questions
Similar Questions
A person has undertaken a construction job. The probabilities are 0.80 that there will be a strike, 0.70 that the construction job will be completed on time if there is no strike, and 0.4 that the construction job will be completed on time if there is a strike. Determine the probability that the construction job will be completed on time.
View SolutionIn a building programme the event that all the materials will be delivered at the correct time is M, and the event that the building programme will be completed on time is F. Given that P(M)=0.8&P(M∩F)=0.65.IfP(F)=0.7, find the probability that the building program me will be completed on time if all the materials are not delivered at the correct time.
View Solution
Knowledge Check
- Question 1 - Select One
A man takes the contract of construction work. The probability is 0.30, if there will be no strike. The probability that the construct work will be completed on time are 0.8 and 0.3 in cases of no strike and in case strike respectively. Find the probability that the construction work will be completed in time.
A0.34B0.56C0.64D0.45 - Question 2 - Select One
25 men can complete a job in 30 days. After how many days should the strength of work force be increased by 50 men so that the work will be completed 23rd in of the actual time:
A15B10C18D5 - Question 3 - Select One
A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
A4/3 daysB3 daysC3 daysD12 days
If 900 persons can finish the construction of a building in 40 days, how many persons are needed to complete the construction of building in 25 days.
View SolutionAnil is twiceas efficient as Binay. If Anil can complete a job in 20 days less as compared to Binay, how much time will they take to complete the job together?
View SolutionA man starts a job, working at the rate of 1 unit a day. After each day, another man joins the working group. The man who joins on the xth day of the job works until the job is completed, at x units per day.The job is completed in 4 days. The time the man who started the work would have taken to complete the job alone is (in days) :
View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If the ratio of the number of days for which D and C worked on job Y is 12:5 and completed the work then find the difference between number of days for which C and D worked.View SolutionA company has a job to prepare certain no. of cans and there are three machines A, B & C for this job. A can complete the job in 3 days, B can complete the job in 4 days and C can complete the job in 6 days. How many days the company will take to complete job if all the machines are used simultaneously?
A)4 days
B)4/3 days
C)3 days
D)12 daysView Solution