Question

If 15 men can finish a piece of work in 20 days however it takes 24 women to finish it in 20 days. If 10 men and 8 women undertake to complete the work then they will take: a 20 days b 30 days c 10 days d 15 days

Text Solution
Verified by Experts

Correct option a 20 days Explanation:According to the question  15 men = 20 days 300 men = 1 das …..i 24 women = 20 days 480 women = 1 days ….ii Compare equation i and ii 300 men = 480 women 5 men = 8 women…..iii 10 men + 8 women = ? 10 men + 5 men = ? 15 men = ? 15 men × 20 days = 15 men × x days x = 20 daysAlternate:-15 M ×20 days = 24 W × 20 daysM/W = 8/5So 1 man work 8 units work in one day And 1 women work 5 units work in one day.Total work = hence 10 M+ 8 W Work whole work in ‘D’ days10 M +8 W× D = 15 × 8 × 20 10×8 + 8×5 × D = 15 × 8 × 20 80 + 40 × D = 15 × 8 × 20 D = 20 days


Related Solutions