Question

If 25 laborers take 10 days to do a piece of work, how many days will it take if the number of laborers is reduced by 5?

A

12.5 days

B

36 days

C

34.5 days

D

37.5 days

Text Solution
Verified by Experts

Given Data:

Number of laborers initially = 25

Time taken by these laborers to complete the work = 10 days

Reduction in the number of laborers = 5

Concept/Formulas Used:

Use the principle of Work and Time, which implies that the time taken to complete a work is inversely proportional to the number of workers.

Solution:

Total work (W) can be considered as (Number of workers × Time taken)

⇒ W = 25 laborers × 10 days

The same work has to be done by (25 - 5) laborers = 20 laborers

Work = Number of workers × Time taken

So, time taken by 20 laborers will be (W / Number of workers)

⇒ T = W / 20

W = 25 laborers × 10 days

⇒ W = 250 labor-days

T = 250 labor-days / 20 laborers

⇒ T = 12.5 days

Hence, the correct answer is 12.5 days.

Updated on:21/07/2023