If 25 laborers take 10 days to do a piece of work, how many days will it take if the number of laborers is reduced by 5?
12.5 days
36 days
34.5 days
37.5 days
Given Data:
Number of laborers initially = 25
Time taken by these laborers to complete the work = 10 days
Reduction in the number of laborers = 5
Concept/Formulas Used:
Use the principle of Work and Time, which implies that the time taken to complete a work is inversely proportional to the number of workers.
Solution:
Total work (W) can be considered as (Number of workers × Time taken)
⇒ W = 25 laborers × 10 days
The same work has to be done by (25 - 5) laborers = 20 laborers
Work = Number of workers × Time taken
So, time taken by 20 laborers will be (W / Number of workers)
⇒ T = W / 20
W = 25 laborers × 10 days
⇒ W = 250 labor-days
T = 250 labor-days / 20 laborers
⇒ T = 12.5 days
Hence, the correct answer is 12.5 days.
Time taken by these laborers to complete the work = 10 days
Reduction in the number of laborers = 5
Concept/Formulas Used:
The same work has to be done by (25 - 5) laborers = 20 laborers
Work = Number of workers × Time taken
So, time taken by 20 laborers will be (W / Number of workers)
W = 25 laborers × 10 days