It takes 8, 12 and 16 days for X, Y and Z respectively to complete a work. How many days will it take to complete the work if X works on it for 2 days, and then Y works on it for until 25% of the work is left for Z to do, and then Z complete the work?
(a) 10 days
(b) 12 days
(c) 8 days
(d) 14 days
Correct option is (b) 12 days
X does the work in 8 days.
∴ In 1 day X does work,
Y does the work in 12 days.
∴ In 1 day Y does work and
Z does the work in 16 days.
∴ In 1 day Z does work.
So, In 2 days, X does 2 × work = work,
Now the work left after Y leaves = 25% work = work
This is done by Z in × 16 days = 4 days.
So Y's share of work = work = work
This work he will do in × 12 days = 6 days.
∴ The total number of days required to finish the work
= (2 + 6 + 4) days
= 12 days.