Question
Select the incorrect statement.:
A
Earliest start of an activity is the early event time of the node it leaves
B
Latest finish of an activity is the late event time of the node it enters
C
Latest start of an activity is its latest finish minus its duration
D
Earliest finish of an activity is the late event time of the node it enters minus its duration
Text Solution
Explanation:
Early Start Time:
- The earliest point in the schedule at which a task can begin.
- EST =
Early Finish Time:
- The earliest point in the schedule at which a task can finish.
- EFT = + tij
NOTE: From the formula and the statement above, we can see that an earlier finish time is the sum of the earlier start time and the event time.
But, statement 4 is saying, we have to minus the duration, which is a false statement.
Latest Start Time:
- The latest point in the schedule at which a task can start without causing a delay.
- LST = - tij
Latest Finish Time:
- The latest point in the schedule at which a task can finish without causing a delay.
- LFT =
Types of float:
1) Total float:
- It is the difference between the maximum time available and the actual time required for the completion of the activity. or It is the difference between the time available for an activity performance and the duration of the activity.
- FT = LST - EST = LFT - EFT =
2) Free float:
- It is the amount of time by which an activity can be delayed without affecting the EST of the succeeding activity.
- FT =
3) Independent float:
- It is the excess of minimum available time over the required activity duration
- FI =
4) Interfering float
- It is the difference between the total float and the free float of an activity.
- FIN = FT - FF
But, statement 4 is saying, we have to minus the duration, which is a false statement.