Question

If 24 laborers take 35 days to do a piece of work, how many days will 42 laborers take to do the same piece of work?

A

5

B

20

C

25

D

10

Text Solution
Verified by Experts

Given Data:

The number of initial laborers is 24.

These laborers can complete the job in 35 days.

We need to find out how long 42 laborers will take to do the same job.

Concept:

The concept used to solve this problem can be expressed as the inverse relationship between work time and workers; if the amount of work remains the same, the time needed to complete it is inversely proportional to the number of workers.

Calculations:

⇒ If 24 laborers complete the work in 35 days, then 1 laborer alone would take 24 × 35 = 840 days.

⇒ If 1 laborer takes 840 days to finish the work, then 42 laborers would take

840 ÷ 42 = 20 days, because each additional laborer reduces the time taken.

Hence, the correct answer is "20".

Updated on:21/07/2023