Question

Ramu and Somu can complete a piece of work in 24 days and 36 days respectively. They started the work but after 6 days Ramu had to leave and Somu alone completed the remaining work. In how many days the whole work was completed?

A

27

B

29

C

31

D

21

Text Solution
Verified by Experts

Given:

Ramu and Somu can complete a piece of work in 24 days and 36 days

They started the work but after 6 days Ramu had to leave and Somu alone completed the remaining work.

Concept Used:

least Common Multiple (LCM) Method

Calculation:

Ramu and Somu can complete a piece of work in 24 days and 36 days

Total Work = LCM of (24 and 36)

⇒ Total Work = 72 unit

Ramu per day efficiency = 72/24 = 3 unit/day

Somu per day efficiency = 72/36 = 2 unit/day

Total work completed by both in 6 days

⇒ 6 × (3 + 2)

⇒ 30 unit

Remaining work = 72 - 30 = 42 unit

Somu completed the remaining work

⇒ 42/2 = 21 days

Total work completed

⇒ 6 + 21

⇒ 27 days

∴ 27 days the whole work was completed.