Question

Z alone can do a work in 240 days. Y is twice as efficient as Z and X is 1.5 times as efficient as Y. How many days will they together take to do the work?

A

80

B

64

C

40

D

48

Text Solution
Verified by Experts

Given:

Z alone can do the work in 240 days

Y is twice as as efficient as Z

X is 1.5 times as efficient as Y

Concept used:

Efficiency is inversely proportional to the time takes to complete a work.

Calculation:

Z alone can do the work in 240 days

One day work of z = 1 / 225

Y is  twice as efficient as Z

So, Y will do the same work in 240/2 = 120 days

X is 1.5 times as efficient as Y

So, X  will do the same work in 120 × (2/3) = 80 days

Total work = LCM of 240, 120 and 80

Efficiency of Z = 240/240 = 1

Efficiency of Y = 240/120 = 2

Efficiency of X = 240/80 = 3

Total time = 240/(3 + 2 + 1) = 40 days.

∴ Option C is correct.