Question
Z alone can do a work in 240 days. Y is twice as efficient as Z and X is 1.5 times as efficient as Y. How many days will they together take to do the work?
A
80
B
64
C
40
D
48
Text Solution
80
64
40
48
Given:
Z alone can do the work in 240 days
Y is twice as as efficient as Z
X is 1.5 times as efficient as Y
Concept used:
Efficiency is inversely proportional to the time takes to complete a work.
Calculation:
Z alone can do the work in 240 days
One day work of z = 1 / 225
Y is twice as efficient as Z
So, Y will do the same work in 240/2 = 120 days
X is 1.5 times as efficient as Y
So, X will do the same work in 120 × (2/3) = 80 days
Total work = LCM of 240, 120 and 80
Efficiency of Z = 240/240 = 1
Efficiency of Y = 240/120 = 2
Efficiency of X = 240/80 = 3
Total time = 240/(3 + 2 + 1) = 40 days.
∴ Option C is correct.