Question

A dummy activity

A

required resources

B

represented by straight bold line

C

does not require any time

D

All of these

Text Solution
Verified by Experts

Explanation:

Dummy activity:

By convention, dummy activities are represented by a dashed arrow on the project network.

In the following diagram both activities A & B have the same beginning and end events.

The above network diagram is incorrect because it breaks the rule of assigning unique numbers to each activity for the purpose of identification. The following network diagram demonstrates the principle of using a dummy activity for overcoming the problem of parallel activities with identical start and finish.

Therefore, a dummy activity is created to make activities with common starting and finishing events distinguishable and also to identify and maintain the proper precedence relationship between activities.