Question

A, B, and C can do a piece of work in 16, 24, and 32 days respectively. They start together, but C leaves after 4 days and A leaves 6 days before the completion of the work. In how many days will the work be completed?

A

12 days

B

15 days

C

9 days

D

14 days

Text Solution
Verified by Experts

Given:

A, B, and C can complete the work in 16, 24, and 32 days respectively. 

They start together, but C leaves after 4 days and A leaves 6 days before the completion of the work.

Concept used:

Total work = work done each day × total time taken (in days)

Calculation:

LCM (16, 24, 32) = 96

Let the total work be LCM for the time taken by them.

Thus, total work = 96 units

efficiency,

A makes a day = 96 ÷ 16 = 6 units

B makes a day = 96 ÷ 24 = 4 units

C does a day = 96 ÷ 32 = 3 units

The entire work is completed in P days.

According to the question,

6 × (P - 6) + 4 × P + 3 × 4 = 96

⇒ 10P = 96 + 36 - 12

⇒ P = 12

∴ The work will be completed in 12 days.   

Updated on:21/07/2023