Question

A and B can complete a work in 4 days, B and C can finish the same work in 8 days, A and C can finish the same work in 6 days. How many days will be required to finish the work if all the three start working together?

A

3 11 13 days

B

3 9 13 days

C

3 7 13 days

D

3 6 13 days

Text Solution
Verified by Experts

Given:

A and B can complete a work in 4 days

B and C can finish the same work in 8 days

A and C can finish the same work in 6 days

Formula used:

Work done = time × efficiency

Calculation:

Total Work = LCM of (4, 8 , 6) = 48

Efficiency of A + B = 48/4 = 12

Efficiency of B + C = 48/8 = 6

Efficicency of A + C = 48/6 = 8

Combined efficiency of A + B + C  ⇒ 2(A + B + C) = 26 ⇒ A + B + C = 13

Total time taken by A + B + C = 48/13 ⇒  3 9 13

∴ The correct answer is  3 9 13 .

Updated on:21/07/2023