Question

Which one of the following statements is correct?

A

PERT is commonly used in the construction work.

B

PERT is suitable for the estimation of activity duration where high levels of uncertainty is there.

C

PERT does not provide time duration.

D

PERT is a deterministic approach. for estimating the time duration of an activity.

Text Solution
Verified by Experts

Explanation:

Programme Evaluation and Review Technique (PERT):

  • Pert was developed by the U.S. Navy during the late 1950s to accelerate the development of the Polaris Fleet Ballistic Missile.
  • PERT, is an abbreviated form that stands for, Programme Evaluation and Review Technique and is used for planning, scheduling, and monitoring the project.
  • Development of this weapon involved the coordination of the work of private contractors, a management consulting firm, and the Lockheed Missile System Division.
  • In PERT three time estimates are made.
  • PERT follows the probabilistic approach and absorbs the uncertainties into the time estimates for activity and project durations.
  • The time estimate of activity has a greater range of variation and hence greater uncertainty, therefore probabilistic approach is used.
  • In PERT time is directly proportional to time hence minimum cost will be achieved corresponding to minimum completion time.
  • PERT is suitable for new projects.
  • In PERT each activity follows β distribution.

​Hence option (2) is the correct answer.