Question

Which of the following statements are correct? A. Direct cost increases with duration. B. Direct cost decreases with duration. C. Indirect cost increases with duration. D. Indirect cost decreases with duration.

A

C

B

A and B

C

B

D

B and C

Text Solution
Verified by Experts

Concept:

Project Cost:

Total project cost is the sum of two separate costs:

(a) The direct cost for accomplishing the work, and 

(b) The indirect cost related to the control or direction of that work, financial overhead, lost production, and the hike, etc.

Direct Project Cost:

​​​These include labour cost, material cost, equipment cost etc.

  • The direct cost curve, having many segments, thus falls with an increase in duration. However, the total indirect cost curve rises with the increase in duration.
  • The project has the highest cost corresponding to the crash duration and has a normal cost corresponding to the normal duration.

Indirect Project Cost:

  • Indirect costs on a project are those expenditures that cannot be apportioned or clearly allocated to the individual activities of a project but are assessed as a whole.
  • The indirect cost includes the expenditure related to administrative and establishment charges, overhead, supervision, expenditure on a central store organization, loss of revenue, lost profit, penalty, etc.
  • The indirect cost rises with increased duration, considering only overhead and supervision. It is represented by a straight line, with a slope equal to daily overhead.

So the correct answer is Option 4

Updated on:21/07/2023