Question

Which one of the following statements is NOT correct related to total float?

A

Total float of an activity is obtained by subtracting its early start time from its late start time.

B

Subtracting the early finish from late finish provides total float.

C

Activities with zero total float is called critical activities.

D

Total float can be calculated by subtracting its early finish time from the earliest of the early start time of the activities directly following.

Text Solution
Verified by Experts

Explanation:

Float:

  • Float indicates the time by which, the starting or finishing of an activity can be delayed without affecting the project completion time.
  • Float is associated with an activity and is analogous to the term slack.

Total float (FT):

  • The difference between the maximum time available and the actual time required for the completion of the activity.
  • Maximum available time we can get when activity starts at Earliest start time and finishes by latest finish time i.e.

FT = Maximum available Time - Actual time required.

Maximum available time = LFT - EST

FT = LST - EST = LFT - EFT

Where LFT = latest finish time, EST = earliest start time, LST = latest start time, EST = earliest start time

FT = 0, For critical path and activities with zero total float is called critical activities.

FT < 0, For supercritical path

FT > 0, For Subcritical path

Free Float:

  • It is defined as the amount of time by which an activity can be delayed without affecting the EST of the succeeding activity.
  • In other words, it is that portion of total float that can be used by an activity without delaying any succeeding activity.

Independent Float:

  • It is the amount of time by which an activity can be delayed when all the preceding activities are completed as late as possible and all succeeding activities start as early as possible.
  • Independent float can also be defined as the excess of minimum available time over the required activity duration.

Interfering Float:

  • It is defined as the difference between the total float and free float of an activity.
  • It is also equal to the slack of head event of head activity as shown below

​Since option (4) is not correct regarding total float. Hence option (4) is the correct answer.

Updated on:21/07/2023