Question

A and B can finish a work in 30 days, B and C in 40 days while C and A in 60 days. How long will they take to finish it while working all together?

A

20 2 3 days

B

26 2 3 days

C

22 1 3 days

D

25 2 3 days

Text Solution
Verified by Experts

Concept Used:-

When a work piece is completed in n number of days, then the in one day the part of work completed will be 1/n.

Explanation:-

Given that, A and B can finish a work in 30 days. So, one day work of A and B,

⇒ A + B = 1 / 30 .....(1)

Also, B and C can finish a work in 40 days. So, one day work of B and C,

⇒ B + C = 1 / 40 .....(2)

Similarly, C and A can finish the work in 60 days. So, one day work of C and A,

⇒ C + A = 1 / 60 .....(3)

Now add all the three equation together,

( A + B ) + ( B + C ) + ( C + A ) = 1 30 + 1 40 + 1 60 2 A + 2 B + 2 C = 4 + 3 + 2 120 2 ( A + B + C ) = 4 + 3 + 2 120 A + B + C = 9 120 × 2 A + B + C = 3 80 This is one day work of when all three work together. Now, the time they take to complete the work,

T = 1 3 80 T = 80 3 T = 26 2 3

So, the time required to finish the work while working all together is 26 2 3 days.

Hence, the correct option is 2.

Updated on:21/07/2023