Question
A and B can finish a work in 30 days, B and C in 40 days while C and A in 60 days. How long will they take to finish it while working all together?
A
20 days
B
26 days
C
22 days
D
25 days
Text Solution
20 days
26 days
22 days
25 days
Concept Used:-
When a work piece is completed in n number of days, then the in one day the part of work completed will be 1/n.
Explanation:-
Given that, A and B can finish a work in 30 days. So, one day work of A and B,
⇒ A + B = 1 / 30 .....(1)
Also, B and C can finish a work in 40 days. So, one day work of B and C,
⇒ B + C = 1 / 40 .....(2)
Similarly, C and A can finish the work in 60 days. So, one day work of C and A,
⇒ C + A = 1 / 60 .....(3)
Now add all the three equation together,
This is one day work of when all three work together. Now, the time they take to complete the work,
So, the time required to finish the work while working all together is 26 days.
Hence, the correct option is 2.