Question

If 72 workers can do a piece of work in 36 days, then in how many days will 54 workers complete the same work?

A

42

B

48

C

46

D

44

Text Solution
Verified by Experts

Concept used:

Less Men, means more Days {Indirect Proportion}

Calculation:

Let the number of days be x then,

54 : 72 : : 36 : x

⇒ 54/72 = 36/x

⇒ x = (72 × 36)/54 = 48 days

∴ 48 days will be required to get work done by 54 workers.

We have written 54 : 36 rather than 54 : 36, in indirect proportion, if you get it then chain rule is clear to you .

Shortcut Trick

M1 × D1 = M2 × D2

Where,

M1 = First man

D1 = First day

M2 = Second man

D2 = Second day

According to the question:

M1 = 72

D1 = 36

M2 = 54

D2 = x days

M1 × D1 = M2 × D2

⇒ 72 × 36 = 54 × x

⇒ x = (72 × 36)/54 = 48 days

∴ 48 days will be required to get work done by 54 workers.