Question
If 72 workers can do a piece of work in 36 days, then in how many days will 54 workers complete the same work?
A
42
B
48
C
46
D
44
Text Solution
42
48
46
44
Concept used:
Less Men, means more Days {Indirect Proportion}
Calculation:
Let the number of days be x then,
54 : 72 : : 36 : x
⇒ 54/72 = 36/x
⇒ x = (72 × 36)/54 = 48 days
∴ 48 days will be required to get work done by 54 workers.
We have written 54 : 36 rather than 54 : 36, in indirect proportion, if you get it then chain rule is clear to you .
Shortcut Trick
M1 × D1 = M2 × D2
Where,
M1 = First man
D1 = First day
M2 = Second man
D2 = Second day
According to the question:
M1 = 72
D1 = 36
M2 = 54
D2 = x days
M1 × D1 = M2 × D2
⇒ 72 × 36 = 54 × x
⇒ x = (72 × 36)/54 = 48 days
∴ 48 days will be required to get work done by 54 workers.