A can do a certain work in 24 days. B is 20% more efficient than A. Both worked together for 5 days. C alone completed the remaining work in days. A and C together can complete the original work in:
12 days
9 days
8 days
6 days
12 days
9 days
8 days
6 days
Given:
A can do a certain work in 24 days.
B is 20% more efficient than A.
Both worked together for 5 days.
C alone completed the remaining work in i.e. 6.5 days.
Concept used:
Total work = Efficiency (Work done per day) × Total time taken
Efficiency (work done per day) of workers is inversely proportional to the time taken by workers to complete a particular task.
Calculation:
Time taken by B to complete the work alone = 24 ÷ (1 + 20%)
⇒ 20 days
Let the total work be 120 units
Efficiency of A = 120/24 = 5 units a day
Efficiency of B = 120/20 = 6 units a day
Work done in 5 days by A and B together = 5(5 + 6)
⇒ 55 units
Remaining work = 120 - 55 = 65 units
Efficiency of C = 65 ÷ 6.5 = 10 units a day
A and C together can complete the original work in = 120 ÷ (5 + 10)
⇒ 8 days
∴ A and C together can complete the original work in 8 days.