Question

A can do a certain work in 24 days. B is 20% more efficient than A. Both worked together for 5 days. C alone completed the remaining work in 6 1 2 days. A and C together can complete the original work in:

A

12 days

B

9 days

C

8 days

D

6 days

Text Solution
Verified by Experts

Given:

A can do a certain work in 24 days.

B is 20% more efficient than A.

Both worked together for 5 days.

C alone completed the remaining work in  6 1 2  i.e. 6.5 days.

Concept used:

Total work = Efficiency (Work done per day) × Total time taken

Efficiency (work done per day) of workers is inversely proportional to the time taken by workers to complete a particular task.

Calculation:

Time taken by B to complete the work alone = 24 ÷ (1 + 20%)

⇒ 20 days

Let the total work be 120 units

Efficiency of A = 120/24 = 5 units a day

Efficiency of B = 120/20 = 6 units a day

Work done in 5 days by A and B together = 5(5 + 6)

⇒ 55 units

Remaining work = 120 - 55 = 65 units

Efficiency of C = 65 ÷ 6.5 = 10 units a day

A and C together can complete the original work in = 120 ÷ (5 + 10)

⇒ 8 days

∴ A and C together can complete the original work in 8 days.