Question

PERT requires

A

single time estimate

B

double time estimate

C

triple time estimate

D

None of the above

Text Solution
Verified by Experts

Explanation:

A project may be defined as a combination of interrelated activities which must be executed in a certain order before the entire task can be completed.

The aim of planning is to develop a sequence of activities of the project so that the project completion time and cost are properly balanced.

To meet the objective of systematic planning, the management has evolved several techniques applying network strategy.

PERT (Programme Evaluation and Review Technique) and CPM (Critical Path Method) are network techniques which have been widely used for planning, scheduling and controlling the large and complex projects.

Difference between PERT and CPM (Critical Path Method)

PERT

CPM

1. Probabilistic approach

1. Deterministic approach

2. Three-time estimate

2. One - time estimate

3. Event oriented network model

3. Activity-oriented network model

4. The slack concept is used

4. Float concept is used

5. Project crashing is not possible

5. Project crashing is possible

6. Deals with probabilistic time estimates

6. Deals with deterministic time estimates

Updated on:21/07/2023