Question

Consider the spreadsheet given below: A B C 1 Project Number of Days 2 A 15 3 A 20 4 B 30 5 A 10 6 B 10 7 A 5 What is the output of the following formula in Cell C1? =SUMIF (A2 : A7, "A", B2 : B7)

A

90

B

80

C

50

D

20

Text Solution
Verified by Experts

The output of the following formula in Cell C1: =SUMIF(A2:A7, "A", B2:B7) will be option 3)50.

Important Points

In this table, we have a list of projects and the number of days it took to complete them.

Now, let's say we want to calculate the total number of days it took to complete all projects with the name "A". We can use the SUMIF formula to do that.

Here's how the formula works:

So, the formula will add these values up and return the output of 50..

Confusion Points

The reason why 90 is not the correct answer is that it would be the sum of all the values in the Number of Days column, regardless of the value in the Project column. In other words, it would be the total number of days spent on all projects, not just project A.

The SUMIF function in cell C1 only includes the values in the Number of Days column that corresponds to the project named "A". Therefore, the sum of the values in the Number of Days column for project A is 15 + 20 + 10 + 5 = 50, which is the result of the SUMIF function.

However, the question asks for the output of the formula in cell C1, which is =SUMIF(A2:A7, "A", B2:B7). This formula specifically tells Excel to sum up the values in the Number of Days column only for the rows where the Project column is "A". Therefore, the correct answer is 50, not 90

Alternate Method

We start with the original table, which has two columns: Project and Number of Days.

The formula in cell C1 is =SUMIF(A2:A7, "A", B2:B7). This formula tells Excel to sum up the values in the Number of Days column (column B) if the corresponding value in the Project column (column A) is "A".

The SUMIF function takes three arguments:

Excel evaluates each cell in the Project column from A2 to A7. If the cell contains "A", the corresponding value in the Number of Days column is included in the sum. If the cell does not contain "A", the value in the corresponding cell in the Number of Days column is not included.

Here's how Excel evaluates each row in the original table:

The values that are included in the sum are: 15 + 20 + 10 + 5 = 50.

Therefore, the final result of the formula in cell C1 is 50, which is the sum of the values in the Number of Days column that corresponds to projects with the name "A"

Updated on:21/07/2023