Question

For walls, column and vertical faces of all structural members, the formwork is generally removed after

A

7 days

B

14 days

C

1 days

D

3 days

Text Solution
Verified by Experts

Concept:

As per IS 456 2000, minimum period before striking formwork for various components are as follows-

Type of Formwork Minimum Period
Before Striking
Formwork
Vertical formwork to columns,
walls, beams
16-24 h
Soffit formwork to slabs
(Props to be re-fixed
immediately after removal
of formwork)
3 days
Soffit formwork to beams
(Props to be re-fixed
immediately after removal
of formwork)
7 days
Props to slabs:1) Spanning up to 4.5 m
2) Spanning over 4.5 m

7 days

14 days

Props to beams and arches: 1) Spanning up to 6 m
2) Spanning over 6 m

14 days

21 days