Question
For walls, column and vertical faces of all structural members, the formwork is generally removed after
A
7 days
B
14 days
C
1 days
D
3 days
Text Solution
Concept:
As per IS 456 2000, minimum period before striking formwork for various components are as follows-
Type of Formwork
Minimum Period
Before Striking
Formwork
Vertical formwork to columns,
walls, beams
16-24 h
Soffit formwork to slabs
(Props to be re-fixed
immediately after removal
of formwork)
3 days
Soffit formwork to beams
(Props to be re-fixed
immediately after removal
of formwork)
7 days
Props to slabs:1) Spanning up to 4.5 m
2) Spanning over 4.5 m
7 days
14 days
Props to beams and arches: 1) Spanning up to 6 m
2) Spanning over 6 m
14 days
21 days
Before Striking
Formwork
walls, beams
(Props to be re-fixed
immediately after removal
of formwork)
(Props to be re-fixed
immediately after removal
of formwork)
2) Spanning over 4.5 m
7 days
14 days
2) Spanning over 6 m
14 days
21 days