Question

Fill in the blank with the correct option: Shuttering of beams spanning over 6 m should be removed in ________ .

A

10 days

B

21 days

C

5 days

D

7 days

Text Solution
Verified by Experts

Concept:

As per IS 456:2000, the minimum period before striking formwork is as follows:

Type of Formwork

Minimum Period Before Striking Formwork

Vertical formwork to columns, walls, beams.

16 - 24 h (1 Day)

Soffit formwork to slabs

3 days

Soffit formwork to beams

7 days

Props to slabs

a. Spanning up to 4.5 m

b. Spanning over 4.5 m

 

7 days

14 days

Props to beams and arches

a. Spanning up to 6 m

b. Spanning over 6 m

 

14 days

21 days

Hence, shuttering of beams spanning over 6 m should be removed in 21 days. 

Updated on:21/07/2023