Question
Fill in the blank with the correct option: Shuttering of beams spanning over 6 m should be removed in ________ .
A
10 days
B
21 days
C
5 days
D
7 days
Text Solution
Concept:
As per IS 456:2000, the minimum period before striking formwork is as follows:
Type of Formwork
Minimum Period Before Striking Formwork
Vertical formwork to columns, walls, beams.
16 - 24 h (1 Day)
Soffit formwork to slabs
3 days
Soffit formwork to beams
7 days
Props to slabs
a. Spanning up to 4.5 m
b. Spanning over 4.5 m
7 days
14 days
Props to beams and arches
a. Spanning up to 6 m
b. Spanning over 6 m
14 days
21 days
Hence, shuttering of beams spanning over 6 m should be removed in 21 days.
Type of Formwork
Minimum Period Before Striking Formwork
Vertical formwork to columns, walls, beams.
16 - 24 h (1 Day)
Soffit formwork to slabs
3 days
Soffit formwork to beams
7 days
Props to slabs
a. Spanning up to 4.5 m
b. Spanning over 4.5 m
7 days
14 days
Props to beams and arches
a. Spanning up to 6 m
b. Spanning over 6 m
14 days
21 days