Question

Which one of the following is NOT considered for the estimation of activity duration?

A

Evaluate activities one at a time, independently of all others.

B

For each activity, assume a normal level of manpower and or equipment.

C

If time units of working days are being used, assume an exceptional day with maximum working hours.

D

Normal weather conditions is considered for the estimation of duration of each activity.

Text Solution
Verified by Experts

Explanation:

Estimation of Activity Duration or Time Estimation:

  • A project is composed of many diversified activities which contribute to its completion.
  • An important characteristic of any project is its duration. As its effectiveness and economy are often dependent on the project duration.
  • The total project duration depends on the time taken by each activity.
  • Estimation of time required for any activity requires wide experience of similar activities.
  • Evaluate activities one at a time, independently of all others.
  • For each activity, assume a normal level of manpower and or equipment.
  • If time units of working days are being used, assume a normal workday.
  • Normal weather conditions are considered for the estimation of the duration of each activity.
  • Estimation of these time estimates can be done in two ways:
  1. Deterministic approach: The Planner has enough knowledge about the activity and gives a single estimate of the duration which is almost accurate.
  2. Probabilistic Approach: The planner does not have much idea about the activity as there is little or no past history about it. The limits within which the duration will lie are estimated.
  • The time estimate of an activity has a greater range of variation and hence greater uncertainty. therefore probabilistic approach is used.
  • Time estimate of an activity has a narrow range of variation and hence in this case time estimate is deterministic.
  • PERT follows the probabilistic approach and absorbs the uncertainties into the time estimates for activity and project durations.
  • CPM follows the deterministic approach.

​Hence option (3) is correct.

Updated on:21/07/2023