Question

Minimum period before striking formwork in soffit of slabs is

A

1 day

B

3 days

C

14 days

D

28 days

Text Solution
Verified by Experts

Explanation:

Type of formwork Minimum period before sticking formwork
Vertical formwork to columns, beams, and walls 16 - 24 hour
Soffit formwork to slabs (props to be refixed immediately after removal of formwork) 3 days
Soffit formwork to beams (props to be refixed immediately after removal of formwork) 7 days
Props to slab  
  • spanning up to 4.5 m
7 days
  • spanning over 4.5 m
14 days
Props to beams  
  • spanning up to 6 m
14 days
  • spanning over 6 m
21 days

Updated on:21/07/2023