Question
Minimum period before striking formwork in soffit of slabs is
A
1 day
B
3 days
C
14 days
D
28 days
Text Solution
Explanation:
Type of formwork
Minimum period before sticking formwork
Vertical formwork to columns, beams, and walls
16 - 24 hour
Soffit formwork to slabs (props to be refixed immediately after removal of formwork)
3 days
Soffit formwork to beams (props to be refixed immediately after removal of formwork)
7 days
Props to slab
- spanning up to 4.5 m
7 days
- spanning over 4.5 m
14 days
Props to beams
- spanning up to 6 m
14 days
- spanning over 6 m
21 days
- spanning up to 4.5 m
- spanning over 4.5 m
- spanning up to 6 m
- spanning over 6 m