A power plant has a maximum demand of 15 MW. The annual load factor is 50% and annual plant capacity factor is 40%. The operating reserve capacity is
6 MW
3 MW
3.75 MW
7.5 MW
6 MW
3 MW
3.75 MW
7.5 MW
Concept:
Plant capacity factor (Cf): It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period.
.... (1)
Where,
AD is the average demand
Pc is plant capacity
The plant capacity factor is an indication of the reverse capacity of the plant. A power station is so designed that it has some reserve capacity for meeting the increased load demand in the future. Therefore, the installed capacity of the plant is always somewhat greater than the maximum demand on the plant.
Reserve capacity = Plant capacity – Maximum demand
If the maximum demand on the plant is equal to plant capacity, then the load factor and plant capacity factor will have the same value. In such a case, the plant will have no reserve capacity.
Load factor (Lf): The ratio of the average load to the maximum demand during a given period is known as the load factor.
.... (2)
Where MD is the maximum demand.
From equations (1) and (2),
Calculation:
Given that,
Lf = 50% = 0.5
Cf = 40% = 0.4
MD = 15 MW
From the above concept,
Reserve capacity = Plant capacity (Pc) – Maximum demand (MD)
Reserve capacity = 18.75 - 15 = 3.75 MW
⇒ installed capacity = 18.75 MW
Reserve capacity = installed capacity – maximum demand = 18.75 – 15 = 3.75 MW