Question

Earlier Finish time can be regarded as

A

Earliest start time − activity time

B

Earliest start time + activity time

C

Latest finish time + Activity time

D

Latest finish time − devation of activity

Text Solution
Verified by Experts

Concept:

In the case of project management the followings are definitions of various terms:

Duration (D): Duration is the estimated or actual time required to complete a task or an activity.

Earliest start time (ES): It is defined as the earliest possible time at which an activity can start. It is calculated by moving from first to last event in a network diagram.

Earliest finish time (EF): It is the earliest possible time at which an activity can finish.

The relationship between earliest start time, earliest finish time, and duration is given by,

Earliest finish time = Earliest start time + duration of that activity

∴ EF = ES + D

So, option 2 is correct.

EF - ES = D

Latest start time (LS): It is defined as the latest time an activity can start and still allow the project to be completed on the estimated project completion time.

Latest finish time (LF): It is the latest possible time at which an activity can finish and still allow the project to be completed on the estimated project completion time.

Relationship between the latest start time, latest finish time, and duration is given by,

Latest finish time = Latest start time + duration of that activity

∴ LF = LS + D

Updated on:21/07/2023