Question

Crash project duration is obtained by summing the

A

Normal durations for all the activities

B

Crash durations for all activities.

C

Crash durations for all the activities along the critical path were obtained by taking into account the normal duration for all the activities

D

Crash durations for all the activities along the critical path are obtained by taking into account the crash duration for all the activities.

Text Solution
Verified by Experts

Concept:

Crash Project Duration:

Additional Information

Normal time:

Crash time:

Normal cost:

Crash cost:

Cost Slope:

The direct cost curve is a curve that can be approximated by a straight line, depending upon the flatness of the curve.

The slope of this straight is the cost slope.

It is very helpful in the project cost analysis.

C s = C r a s h C o s t N o r m a l C o s t N o r m a l T i m e C r a s h T i m e

Updated on:21/07/2023