Question
For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is ________
A
10 days
B
7 days
C
12 days
D
9 days
Text Solution
10 days
7 days
12 days
9 days
The correct answer is 7 days.
Key Points To calculate the average time for a project activity using the three-point estimation method, you can use the following formula:
Average Time = (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6
In this case, the optimistic time is 4 days, the pessimistic time is 14 days, and the most likely time is 6 days. Plugging these values into the formula, we get:
Average Time = (4 + 4 * 6 + 14) / 6 Average Time = (4 + 24 + 14) / 6 Average Time = 42 / 6 Average Time = 7
Therefore, the average time for the project activity is 7 days.