Question

For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is ________

A

10 days

B

7 days

C

12 days

D

9 days

Text Solution
Verified by Experts

The correct answer is 7 days.

Key Points To calculate the average time for a project activity using the three-point estimation method, you can use the following formula:

Average Time = (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6

In this case, the optimistic time is 4 days, the pessimistic time is 14 days, and the most likely time is 6 days. Plugging these values into the formula, we get:

Average Time = (4 + 4 * 6 + 14) / 6 Average Time = (4 + 24 + 14) / 6 Average Time = 42 / 6 Average Time = 7

Therefore, the average time for the project activity is 7 days.

Updated on:21/07/2023