In PERT, which one of the following is the estimator expects that he may come across some sort of uncertainties and many a time the things will go right?
Optimistic time
Pessimistic time
Likely time
Unlikely time
Optimistic time
Pessimistic time
Likely time
Unlikely time
Explanation:-
PERT (Project Evaluation and Review Technique) -
PERT and CPM are basically time-oriented methods in the sense that they both lead to the determination of a time schedule for the project. The significant difference between the two approaches is that the time estimates for the different activities in CPM were assumed to be deterministic while in PERT these are described probabilistically.
The main objective of the analysis through PERT is to find out the completion of a particular event within the specified date. The PERT approach takes into account the uncertainties. The three-time values are associated with each activity -
1. Optimistic time:
2. Most likely time:-
3. Pessimistic time: