Question

A power plant has load factor = 0.75 and capacity factor = 0.60. If the maximum demand is 80 MW, then find the plant capacity.

A

90 MW

B

135 MW

C

100 MW

D

60 MW

Text Solution
Verified by Experts

Concept:

Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.

L o a d f a c t o r = A v e a r g e l o a d M a x i m u m d e m a n d

Considered the plant is in the operation for T hours

L o a d f a c t o r = A v e a r g e l o a d × T M a x i m u m d e m a n d × T

Plant capacity factor: It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period.

P l a n t c a p a c i t y f a c t o r = A c t u a l e n e r g y p r o d u c e d M a x i m u m e n e r g y t h a t c o u l d h a v e b e e n p r o d u c e d

P l a n t   c a p a c i t y   f a c t o r = A v e r a g e d e m a n d P l a n t c a p a c i t y

A n n u a l p l a n t c a p a c i t y f a c t o r = A n n u a l k W h o u t p u t P l a n t c a p a c i t y × 8760

  • The plant capacity factor is an indication of the reverse capacity of the plant.
  • A power station is so designed that it has some reserve capacity for meeting the increased load demand in the future.
  • The installed capacity of the plant is always somewhat greater than the maximum demand on the plant.


Reserve capacity = Plant capacity – Maximum demand

Calculation:

Given,

load factor = 0.75,

Capacity factor = 0.60

Maximum demand = 80 MW

From above concept,

Average load = maximum demand × load factor

or, Average load = 80 × 0.75 = 60 MW

Hence, Plant Capacity = Average load / capacity factor

or, Plant Capacity = 60 / 0.60 = 100 MW

Updated on:21/07/2023