Theere are 4 people whow can complete a work in 19 days. Individually. The work is started by one of people on the first day. Everyday one more person joins and starting from the 4th days, all of the 4 people work be completed?
614 days
6119days
7 days
7119 days
The correct Answer is:A
(i) Work done in the first three dya is 119+219+319 and find the 4th day onwards the work done is 419
(ii) Part of the work done in first three days 119+219+319=619
∴ Remaining work =1319
(iii) Let required time =(3+x) days.
Related Playlists
Similar Questions
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?
View SolutionA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution40 people can complete a work in 40 days. They started the work together but 5 people had to leave the work on every tenth day. In how much time the work would be completed?
View SolutionTheere are 5 men in group. Each man can complete a job in 35 days. One of them starts it . Starting from the second day, a man joins until the 5th day. Therefore, all the men work together. Find the total time taken to complete the job. ( in days)
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 more men join the work.View Solution25 persons can complete a work in 60 days. They started the work. 10 people left the work after x days. If the whole work was completed in 80 days, then what is the value of x ?
25 व्यक्ति किसी कार्य को 60 दिनों में पूरा कर सकते हैं | उन्होंने कार्य शुरू किया | x दिनों के बाद 10 लोगों ने कार्य छोड़ दिया | यदि पूरा कार्य 80 दिनों में पूरा हुआ, तो x का मान ज्ञात करें |View Solution50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?
View Solution27. 15 people completed a work in 7 days 10 How many days should people take to complete this work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution