Doubtnut Promotions Sticky

The following table gives the information regarding the number of persons employed to do a piece of work and time taken to complete the work:
The following table gives the information  regarding the number of persons employed to do a piece of work and time taken to complete the work:       Plot the line graph for this information.
Plot the line graph for this information.

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for The following table gives the information regarding the number of persons employed to do a piece of work and time taken to complete the work: Plot the line graph for this information. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be

    A12 days
    B10 days
    C9 days
    D8 days
  • Question 1 - Select One

    A is thrice as fast as B. If B can do a piece of work in 60 days, the number of days they take to complete the work is ……..

    A22 days
    B23 days
    C22.5 days
    D23.5 days
  • Question 1 - Select One

    12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?

    A192
    B190
    C180
    D144
  • Question 1 - Select One

    If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

    A4
    B5
    C14
    D10
  • Question 1 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10

Similar Questions