The following table gives the information regarding the number of persons employed to do a piece of work and time taken to complete the work:
Plot the line graph for this information.
Step by step video & image solution for The following table gives the information regarding the number of persons employed to do a piece of work and time taken to complete the work: Plot the line graph for this information. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Related Playlists
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - INTRODUCTION TO GRAPHS EXERCISE - EXERCISE (SUBJECTIVE PROBLEMS) (VERY SHORT ANSWER TYPE)1videos
INTRODUCTION TO GRAPHS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - INTRODUCTION TO GRAPHS EXERCISE - EXERCISE (SUBJECTIVE PROBLEMS) (SHORT ANSWER TYPE)2videos
INTRODUCTION TO GRAPHS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - INTRODUCTION TO GRAPHS EXERCISE - EXERCISE (Assertion & Reason Type)8videos
INTRODUCTION TO GRAPHS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - FOOTSTEPS TOWARDS JEE MAINEXERCISE - Section B (Numerical Value Type Questions)9videos
FOOTSTEPS TOWARDS JEE MAIN
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - LINEAR EQUATIONS IN ONE VARIABLEEXERCISE - Olympiad/HOTS Corner15videos
LINEAR EQUATIONS IN ONE VARIABLE
Knowledge Check
- Question 1 - Select One
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
A12 daysB10 daysC9 daysD8 days - Question 1 - Select One
A is thrice as fast as B. If B can do a piece of work in 60 days, the number of days they take to complete the work is ……..
A22 daysB23 daysC22.5 daysD23.5 days - Question 1 - Select One
12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
A192B190C180D144 - Question 1 - Select One
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
A4B5C14D10 - Question 1 - Select One
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
A40B20C14D10
Similar Questions
The following table gives the information regarding the number of persons employed to a piece of work and time taken to complete the work: No. of persons:, 2, 4, 6, 8 Time taken (in days):, 12, 6, 4, 3 Plot a graph of this information.
View SolutionComplete the following table using given information
View SolutionComplete the following table with correct information with regard to the policy of MNREGA.
View SolutionIf 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is
View SolutionA is thrice as fast as B. If B can do a piece of work in 60 days, the number of days they take to complete the work is ……..
View Solution