Doubtnut Promotions Sticky

The following table gives the information regarding the number of persons employed to a piece of work and time taken to complete the work: No. of persons:, 2, 4, 6, 8 Time taken (in days):, 12, 6, 4, 3 Plot a graph of this information.

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for The following table gives the information regarding the number of persons employed to a piece of work and time taken to complete the work: No. of persons:, 2, 4, 6, 8 Time taken (in days):, 12, 6, 4, 3 Plot a graph of this information. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?

    A192
    B190
    C180
    D144
  • Question 1 - Select One

    If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

    A4
    B5
    C14
    D10
  • Question 1 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10
  • Question 1 - Select One

    Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?

    A3
    B2
    C4
    D1
  • Question 1 - Select One

    Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?

    A3
    B2
    C4
    D1
  • Question 1 - Select One

    If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.

    A6 days
    B5 days
    C4 days
    D3 days
  • Question 1 - Select One

    If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.

    A6 days
    B5 days
    C4 days
    D3 days
  • Question 1 - Select One

    Where 6 men and 9 women can complete a piece of work in 10 days, What is the time taken by 4 men and 6 women to complete it ?

    A10 days
    B12 days
    C15 days
    D18 days
  • Question 1 - Select One

    Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in

    A9 days
    B6 days
    C5 days
    D3 days

Similar Questions