The following table gives the information regarding the number of persons employed to a piece of work and time taken to complete the work: No. of persons:, 2, 4, 6, 8 Time taken (in days):, 12, 6, 4, 3 Plot a graph of this information.
Video Solution
|
Answer
Step by step video & image solution for The following table gives the information regarding the number of persons employed to a piece of work and time taken to complete the work: No. of persons:, 2, 4, 6, 8 Time taken (in days):, 12, 6, 4, 3 Plot a graph of this information. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Updated on:21/07/2023
Related Playlists
Knowledge Check
- Question 1 - Select One
12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
A192B190C180D144 - Question 1 - Select One
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
A4B5C14D10 - Question 1 - Select One
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
A40B20C14D10 - Question 1 - Select One
Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
A3B2C4D1 - Question 1 - Select One
Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
A3B2C4D1 - Question 1 - Select One
If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 days - Question 1 - Select One
If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 days - Question 1 - Select One
Where 6 men and 9 women can complete a piece of work in 10 days, What is the time taken by 4 men and 6 women to complete it ?
A10 daysB12 daysC15 daysD18 days - Question 1 - Select One
Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in
A9 daysB6 daysC5 daysD3 days