Doubtnut Promotions Sticky

Ten men, working for 6 days of 10 hours each, finish 521 of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:=24

|
Answer

Step by step video, text & image solution for Ten men, working for 6 days of 10 hours each, finish (5)/(21) of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days ? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Similar Questions