Doubtnut Promotions Sticky

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in the order AB:
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in the order AB:      Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.

Text Solution
Verified by Experts

The correct Answer is:Total Elapsed Time T = 55 minutes
Idle Time for machine A =3 minutes
Idle Time for machine B = 9 minutes

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Related Playlists


Similar Questions