Doubtnut Promotions Sticky

Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Since 15 men take 10 days working 12 hours per day, the total work done measured in terms of man-hours is 15×1012.
When 10 men are required to complete the same job in 20 days working h hours a day, work done =10×20×h. But 10×20×h=15×10×12. Hence the number of hours for which they should work per day is 15×10×1210×20=9.
10 men can complete the work in 20 days working for 9 hours per day.
Hence, in general we can say that:
If M1 men can do W1 units of work in D1 days working H1 hours per day and M2 men can do
W2 untis of work in D2 days working H2 hours per day, then M1D1H1W1=M2D2H2W2

|
Updated on:21/07/2023

Related Playlists


Similar Questions