Doubtnut Promotions Sticky

Amir and Akbar can finish a task in 30 days and 15 days, respectively. Akbar worked on the task for 8 days and left the job. In how many days can Amir alone finish the remaining work?
आमिर और अकबर क्रमशः 30 दिनों और 15 दिनों में एक कार्य पूरा कर सकते हैं। अकबर ने 8 दिनों तक कार्य किया और नौकरी छोड़ दी। शेष कार्य को आमिर अकेले कितने दिनों में पूरा कर सकता है?

A

14 days

B

15 days

C

16 Days

D

17 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Determine the work done by Amir and Akbar in one day.
- Amir can complete the task in 30 days. Therefore, in one day, Amir can complete 130 of the work.
- Akbar can complete the task in 15 days. Therefore, in one day, Akbar can complete 115 of the work.

Step 2: Calculate the combined work done by Amir and Akbar in one day.
- The combined work done by Amir and Akbar in one day is:
Combined work=130+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 30 and 15 is 30.
130+230=330=110
- Thus, together, they can complete 110 of the work in one day.

Step 3: Calculate the total work done by Akbar in 8 days.
- In 8 days, the work done by both Amir and Akbar is:
Work done in 8 days=8×110=810=45

Step 4: Determine the remaining work after Akbar leaves.
- If 45 of the work is completed, then the remaining work is:
Remaining work=145=15

Step 5: Calculate how many days Amir will take to finish the remaining work.
- Amir completes 130 of the work in one day. To find out how many days he needs to complete 15 of the work, we set up the equation:
Days required=Remaining workWork done by Amir in one day=15130=15×301=6

Final Answer:
Amir can finish the remaining work in 6 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A512
    B5
    C8
    D6